Contract No: HK/2011/07 Wanchai
Development Phase II and Central Wanchai Bypass Sampling, Field
Measurement and Testing Works (Stage 2) Environmental Permit no. EP-356/2009, Further Evironmental
permit nos. fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 ,Fep-05/356/2009,
Fep-06/356/2009 and FEP-07/356/2009 Monthly Environmental Monitoring & Audit Report
- August 2014 -
|
CLIENTS: |
|
Civil Engineering and
Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point 181-185
Gloucester Road, Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified
by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
September 2014 |
|
|
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. Status of Regulatory Compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real-time Noise Monitoring
6.2 Real-time noise Monitoring
6.5 Review of the Reasons for and the Implications of
Non-compliance
6.6 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction Impact due to the Concurrent
Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary of Water Quality Monitoring Exceedances in
Reporting Month
Table II Summary of Enhanced Dissolved Oxygen Monitoring
Exceedances in Reporting Month
Table 2.1 Schedule 2 Designated Projects under this Project
Table 2.2 Details of Individual Contracts under the Project
Table 2.3 Contact Details of Key Personnel
Table 3.4 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/01
Table 3.5 Summary of submission status under FEP-02/356/2009
Condition
Table 3.6 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/02
Table 3.7 Summary of submission status under FEP-03/356/2009
Condition
Table 3.8 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/15
Table 3.9 Summary of submission status under FEP-04/356/2009
Condition
Table 3.10 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2010/06
Table 3.11 Summary of submission status under EP-356/2009 and
FEP-05/356/2009 Condition
Table 3.12 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/19
Table 3.13 Cumulative Summary of Valid Licences and Permits
under Contract no. HK/2012/08
Table 3.14 Summary of submission status under EP-356/2009 and
FEP-06/356/2009 Condition
Table 3.15 Cumulative Summary of Valid Licences and Permits
under Contract no. HY/2010/08
Table 3.16 Summary of submission status under EP-356/2009 and
FEP-07/356/2009 Condition
Table 4.1 Noise Monitoring Station
Table 4.2 Real Time Noise Monitoring Station
Table 4.3 Air Monitoring Station
Table 4.4 Marine Water Quality Stations for Water Quality
Monitoring
Table 4.5 Marine Water Quality Monitoring Frequency and
Parameters
Table 4.6 Marine Water Quality Stations for Enhanced Water
Quality Monitoring
Table 4.7 Marine Water Quality Stations for Additional DO
Monitoring
Table 5.2 Noise Monitoring Station for Contract nos. HK/2009/01,
HK/2009/02 and HK/2010/06
Table 5.3 Noise Monitoring Station for Contract no. HY/2009/15
Table 5.4 Noise Monitoring Station for Contract no. HY/2009/19
Table 5.5 Real
Time Noise Monitoring Station for Contract no. HY/2010/08
Table 5.6 Real
Time Noise Monitoring Station for Contract no. HY/2009/19
Table 5.7 Air
Monitoring Stations for Contract no. HK/2009/01
Table 5.8 Air Monitoring Station for Contract no. HK/2009/02
Table 5.9 Air Monitoring Station for Contract no. HY/2009/15
Table 5.10 Air
Monitoring Stations for Contract no. HY/2009/19
Table 5.12 Water
Monitoring Stations for Contract no. HK/2009/01
Table 5.13 Water
Monitoring Stations for Contract no. HK/2009/02
Table 5.14 Water
Monitoring Stations for Contract no. HK/2010/06
Table 5.15 Water
Monitoring Stations for Contract no. HY/2009/15
Table 5.16 Water
Monitoring Stations for Contract no. HY/2009/19
Table 5.17 Summary
of Water Quality Monitoring Exceedances in Reporting Month
Table 5.18 Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Table 5.19 Details of Waste Disposal for Contract no. HK/2009/01
Table 5.20 Details of Waste Disposal for Contract no. HK/2009/02
Table 5.21 Details of Waste Disposal for Contract no. HY/2009/15
Table 5.22 Details of Waste Disposal for Contract no. HK/2010/06
Table 5.23 Details of Waste Disposal for Contract no. HY/2009/19
Table 5.24 Details of Waste Disposal for Contract no. HK/2012/08
Table 5.25 Details of Waste Disposal for Contract
no. HY/2010/08
Table 8.1 Summary of Environmental Inspections for Contract no.
HK/2009/01
Table 8.2 Summary of Environmental Inspections for Contract no.
HK/2009/02
Table 8.3 Summary of Environmental Inspections for Contract no.
HY/2009/15
Table 8.4 Summary of Environmental Inspections for Contract no.
HK/2010/06
Table 8.5 Summary of Environmental Inspections for Contract no.
HY/2009/19
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful Prosecutions
Table 10.1 Construction Activities and Recommended Mitigation
Measures in Coming Reporting Month
lIST OF FIGUREs
Figure 2.2 Project Organization Chart
Figure 4.1 Locations of Environmental Monitoring Stations
lIST OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical Presentations
Appendix 5.4 Water Quality Monitoring Results and Graphical Presentations
Appendix 5.4a Additional Dissolved Oxygen Monitoring Results
Appendix 5.5 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix
6.2 Summary for Notification of
Exceedance
Appendix 10.1 Construction Programme of Individual Contracts
Construction Activities for the Reported Period
¡P
Rock trimming works
Road works
Connection works
of temporary sewage pipe
Lighting
installation
Granolithic
finishing
Reclamation at
WCR2
Excavation works
Construction of
at-grade road
¡P
EVA construction at Eastern Breakwater
¡P
Reinstatement of Eastern Breakwater
¡P
Removal of Seawall Blocks at TPCWAE & TS4
¡P
Demolition of D-Wall at TS2, TPCWAE & TS4
¡P
Underwater Cutting of Temporary Diaphragm
Walls at TS2, TS4 and TPCWAE
Nil
¡P
ELS for box culvert La at Lung King Street
¡P
Filling for seawall rock mound formation
¡P
Filling for reclamation
¡P
Dredging
¡P
Sheet piling
¡P
Rock filling works
¡P
Dredging works
¡P
Seawall blocks installation
Noise
Monitoring
Real-time
Noise Monitoring
Air Quality Monitoring
24hr TSP monitoring at CMA1b was
rescheduled from 14 August 2014 and 20 August 2014 to 15 August 2014 and 21
August 2014 respectively.
24hr TSP monitoring at CMA5a was
rescheduled from 14 August 2014 and 20 August 2014 to 15 August 2014 to 21
August 2014 respectively.
Water Quality Monitoring
WQM
during flood tide was cancelled on 1 August 2014
WQM
during ebb tide was cancelled on 13 August 2014
WQM
during ebb tide was cancelled on 20 August 2014
Table
I Summary of Water Quality
Monitoring Exceedances in Reporting Month
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
||
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2012/08 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
P1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
P3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
P4 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
P5 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 Monitoring started
on 8 Feb 2012 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
Monitoring started
on 29 July 2013 |
RW21-P789 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
HY/2009/15 &
HY/2010/08 |
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
Total |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
- WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.
- 4-week water quality monitoring at
WSD9, WSD10, WSD15, WSD17, C8 and C9 were completed on 6 Feb 2012.
- C8 and C9 were implemented with
respect to HY/2009/19 from 28 Jan 2012.
- C8 & C9 was temporary
suspended on 30 March 2013 due to the marine works for Contract no. HY/2009/19
had been completed on 4 March 2013
- WSD7 and WSD20 water quality
monitoring were temporarily suspended from 27 Apr 2012.
- C2, C3 C4e and C4w water quality monitoring
station was temporarily suspended since 24 Apr 2013
- C5e and C5w water quality
monitoring station was temporarily suspended since 29 July 2013
- WSD21 water quality monitoring
station was temporarily suspended since 12 March 2014
- Maintenance responsibility of
silt screen C1, WSD19, P3, P4 and P5 are under Contract HK/2009/01.
Table
II Summary of Enhanced Dissolved
Oxygen Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
AL |
LL |
AL |
LL |
||
C6 |
0 |
0 |
0 |
0 |
|
C7 |
0 |
0 |
0 |
0 |
|
Ex-WPCWA
SW |
0 |
6 |
0 |
1 |
|
Ex-WPCWA
SE |
1 |
6 |
0 |
0 |
|
Total |
1 |
12 |
0 |
1 |
Complaints, Notifications of Summons and Successful
Prosecutions
Site Inspections and Audit
Future Key Issues
Contract no. HK/2009/01 ¡V Wan Chai
Development Phase II ¡V Central ¡VWanchai Bypass at HKCEC
Rock trimming works
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East
¡P
Works of covered walkway at Expo Drive East
¡P
Backfilling works
¡P
ABWF works
¡P
Construction of temporary covered walkway
¡P
Installation of Bridge 1, 2 &3
¡P
Construction of at-grade road
¡P
Installation of street furniture and pavement
works
Contract no. HY/2009/15 ¡V
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)
¡P
Construction works of East Ventilation Shaft
¡P
Removal of Seawall Blocks at TPCWAE & TS4
¡P
Underwater Cutting of Temporary Diaphragm
Walls at TS4 and TPCWAE
¡P
Demolition of D-Wall at TPCWAE &TS4
Contract no. HK/2010/06 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Nil
Contract no. HY/2009/19- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
¡P
Construction of Dolphin Cap
Contract no. HK/2012/08 ¡V Wan Chai Development Phase II ¡V Central- Wan
Chai Bypass at Wan Chai West
¡P
ELS for box culvert La at Lung King Street
¡P
Filling for seawall rock mound formation
¡P
Filling for reclamation
Contract
no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8)
¡P
Rock filling works
¡P
Dredging works
¡P
Seawall block installation
1.1.1. Lam
Geotechnics Limited (LGL) has been appointed to work as the Environmental Team
(ET) under Environmental Permit no. EP-356/2009 and Further Environmental
permit nos. FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009, FEP-05/356/2009,
FEP-06/356/2009 and FEP-07/356/2009 to implement the Environmental Monitoring and Audit
(EM&A) programme as stipulated in the EM&A Manual of the approved
Environmental Impact Assessment (EIA) Report for Wan Chai Development phase II
and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the EM&A
Manual of the approved EIA Report for Central-Wan Chai Bypass and Island
Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2. This
report presents the environmental monitoring and auditing work carried out in
accordance to the Section 10.3 of EM&A Manual and ¡§Environmental
Monitoring and Audit Requirements¡¨ under Particular Specification Section
27.
1.1.3. This
report documents the finding of EM&A works for Environmental Permit no.
EP-356/2009, Further Environmental Permit no. FEP-02/356/2009, FEP-03/356/2009,
FEP-04/356/2009, FEP-05/356/2009, FEP-06/356/2009 and FEP-07/356/2009 during the
period of July 2014 to August 2014. The cut-off date of reporting is at 27th
of each reporting month.
Section 1 Introduction ¡V details the scope and structure of the report.
Section 2 Project
Background ¡V summarizes background and
scope of the project, site description, project organization and contact
details of key personnel during the reporting period.
Section 3 Status of Regulatory Compliance ¡V summarizes the status of valid Environmental Permits /
Licenses during the reporting period.
Section 4 Monitoring
Requirements ¡V summarizes all monitoring
parameters, monitoring methodology and equipment, monitoring locations,
monitoring frequency, criteria and respective event and action plan and
monitoring programmes.
Section 5 Monitoring
Results ¡V summarizes the monitoring
results obtained in the reporting period.
Section 6 Compliance Audit ¡V summarizes
the auditing of monitoring results, all exceedances environmental
parameters.
Section 7 Cumulative Construction Impact due
to the Concurrent Projects ¡V summarizes the relevant cumulative
construction impact due to the concurrent activities of the concurrent Projects.
Section 8 Site Inspection ¡V summarizes the findings of weekly site inspections
undertaken within the reporting period, with a review of any relevant follow-up actions within the reporting period.
Section 9 Complaints, Notification of
summons and Prosecution ¡V summarizes the cumulative statistics on
complaints, notification of summons and prosecution
Section 10 Conclusion
2.1.1. ¡§Wan Chai
Development phase II and Central-Wan Chai Bypass¡¨ and ¡§Central-Wan Chai Bypass
and Island Eastern Corridor Link¡¨ (hereafter called ¡§the Project¡¨) are Designed
Project (DP) under the Environmental Impact Assessment Ordinance (Cap. 499)
(EIAO). The Environmental Impact Assessment (EIA) Reports for Central-Wan Chai
Bypass and Island Eastern Corridor Link (Register No. AEIAR-041/2001) and Wan
Chai Development phase II and Central-Wan Chai Bypass (Register No.:
AEIAR-125/2008) have been approved on 31 August 2001 and 11 December 2008
respectively.
2.1.2. The key
purpose of Wan Chai Development Phase II (WDII) is to provide land at Wan Chai
North and North Point for construction of the Central-Wan Chai Bypass and
Island Eastern Corridor Link (CWB). Land formed under the project will be
developed as a world-class waterfront promenade joining that at the new Central
waterfront for public enjoyment.
2.1.3. There is a
compelling and present need for the CWB to provide relief to the very congested
east-west Connaught Road Central/Harcourt Road / Gloucester Road Corridor (the
Corridor) which is currently operating beyond its capacity. The CWB will
provide relief to the existing congestion along the Corridor and cater for the
anticipated growth of traffic on Hong Kong Island. Without the CWB and its
access roads, there will not be sufficient capacity to serve the heavy traffic
demands at both strategic and local levels.
2.2.1. The
Project is located mainly in Wan Chai North, Causeway Bay and North Point, and
is demarcated by Gloucester Road and Victoria Park Road to the south, Fenwick
Pier Street to the west and Tong Shui Road Interchange to the east, as shown in
Figure 2.1.
2.2.2. The study
area encompasses existing developments along the Wan Chai, Causeway Bay and
North Point shorelines. Major land uses include the Hong Kong Convention &
Exhibition Centre (HKCEC) Extension, the Wan Chai Ferry Pier, the ex-Wan Chai
Public Cargo Working Area (ex-PCWA), the Royal Hong Kong Yacht Club (RHKYC),
the Police Officers¡¦ Club, the Causeway Bay Typhoon Shelter (CBTS) and
commercial and residential developments.
2.2.3. The scope of the Project comprises:
¡P
Land
formation for key transport infrastructure and facilities, including the Trunk
Road (i.e.
CWB) and the associated slip roads for connection to the Trunk Road and for through
traffic from Central to Wan Chai and Causeway Bay. The land formed for the above
transport infrastructure will provide opportunities for the development of an
attractive waterfront promenade for the enjoyment of the public
¡P
Reprovisioning
/ protection of the existing facilities and structures affected by the land
formation works mentioned above
¡P
Extension,
modification, reprovisioning or protection of existing storm water drainage
outfalls, sewerage outfalls and watermains affected by the revised land use and
land formation works mentioned above
¡P
Upgrading
of hinterland storm water drainage system and sewerage system, which would be
rendered insufficient by the land formation works mentioned above
¡P
Provision
of the ground level roads, flyovers, footbridges, necessary transport
facilities and the associated utility services
¡P
Construction
of the new waterfront promenade, landscape works and the associated utility
services
¡P
The
Trunk Road (i.e. CWB) within the study area and the associated slip roads for
connection to the Trunk Road.
2.2.4. The
project also contains various Schedule 2 DPs that, under the EIAO, require
Environmental Permits (Eps) to be granted by the DEP before they may be either
constructed or operated. Table 2.1 summarises the five individual
DPs under this Project. Figure 2.1 shows the locations of these Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated
Project |
EIAO
Reference |
Reason for
inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1. Due to the
multi-contract nature of the Project, there are a number of contracts
sub-dividing the whole works area into different work areas to be commenced.
Contractors of individual contracts will be required by the EP holder to apply
Further Environmental Permits (FEP) such that the impact monitoring stations
are sub-divided accordingly to facilitate the implementation of EM&A
programme and to streamline the EM&A reporting for individual FEP holders
correspondingly.
2.3.2. The
details of individual contracts are summarized in Table 2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract
No. |
Contract Title |
Associated
DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at Hong Kong
Convention and Exhibition Centre |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central ¡V Wan Chai Bypass ¡V North
Point Reclamation |
DP3 |
17 March 2010 (Completed) |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section) |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near Man Yiu Street and Man Kwong
Street |
DP1 |
September 2010 (Completed) |
HY/2009/17 |
Central ¡V Wan Chai Bypass (CWB) at FEHD Whitfield Depot ¡V Advanced
piling works. |
DP1 |
5 October 2010 (Completed) |
HY/2009/18 |
Central ¡V Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
HK/2012/08 |
Wan Chai
Development Phase II Central- Wan Chai Bypass at
Wan Chai West |
DP1,DP2,
DP3 |
10 March 2014 |
HY/2010/08 |
Central- Wanchai Bypass Tunnel ¡V Tunnel (Slip Road 8) |
DP1, DP2, DP3 |
21 March 2013 |
HY/2011/08 |
Central-Wan Chai Bypass (CWB) ¡V Tunnel Buildings,
Systems and Fittings, and Works Associated with Tunnel Commissioning |
DP1 |
To be commenced tentatively on 4th quarter
in 2014 |
2.4.1. Civil
Engineering and Development Department and Highways Department are the overall
project controllers for the Wan Chai Development Phase II and Central-Wan Chai
Bypass respectively. For the construction phase of the Project, Project
Engineer, Contractor(s), Environmental Team and Independent Environmental
Checker are appointed to manage and control environmental issues.
2.4.2. The
proposed project organization and lines of communication with respect to
environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table
2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact
No. |
Contact
Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912 3010 |
|
Chun Wo ¡V Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Joint
Venture Board Representative |
Mr. Simon Liu |
9304 8355 |
2587 1878 |
Deputy Site
Agent |
Mr. Andy Yu |
9648 4896 |
|||
Construction
Manager |
Mr. Terry
Wong |
9757 9846 |
|||
Construction
Manager |
Mr. Wyman
Wong |
9627 2467 |
|||
Construction
Manager |
Mr. Kenneth
Chan |
9160 3850 |
|||
Senior Environmental Engineer |
Ms. Wendy Ng |
9803 0057 |
|||
Assistant
Environmental Engineer |
Miss.
Connie Chan |
6157 7057 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Project
Manager |
Mr. Alfred Leung |
3658-3022 |
2827 9996 |
Quality & Environmental Manager |
Mr. C.P. Ho |
9191 8856 |
|||
China State Construction Engineering (HK) Ltd. |
Contractor under Contract no. HY/2009/15 |
Project Director |
K C Cheung |
3557 6399 |
2566 2192 |
Site Manager |
J H Chen |
3557 6368 |
|||
|
|
Contractor¡¦s Representative |
Andrew Wong |
3557 6358 |
|
|
|
Contractor¡¦s Representative |
Gene Cheung |
3557 6395 |
|
|
|
Senior Project Manager |
Eddie Tang |
35576452 |
|
|
|
Environmental Officer |
Andy Mak |
3557 6347 |
|
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project
Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Eric
Yip |
2529 2068 |
|||
Environmental
Officer |
Clement
Pang |
9735 9200 |
|||
Environmental
Supervisor |
Jacky
Cheung |
9779 2292 |
|||
Chun Wo ¡V CRGL ¡V MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
|
Site Agent |
Mr. Eric Yip |
252902068 |
|||
Environmental Engineer |
Mr. Calvin Leung |
9286 9208 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
Operation Manager (Land) |
Yung Kwok Wah |
9834 1010 |
|||
China State- Leader JV |
Contractor under Contract no. HK/2012/08 |
Project Director |
Andrew Tse |
9137 1811 |
2877 1522 |
Project Manager |
Victor Wu |
9193 8871 |
|||
Deputy Project Manager |
George Cheung |
9268 1918 |
|||
Site Agent |
Paul Lui |
9095 7922 |
|||
Environmental Officer |
James Ma |
9130 9549 |
|||
Environmental Supervisor |
Ching Man, Chan |
6050 4919 |
|||
China State |
Contractor under
Contract no. HY/2010/08 |
Project Director |
Cheung Kit Cheung |
3557 6399 |
2566 8061 |
|
|
Project Manager |
Chan Ying Lun |
3418 3001 |
|
|
|
Deputy Project Manager |
Chris Leung |
3467 4299 |
|
|
|
Site Agent |
Dave Chan |
3467 4277 |
|
|
|
Environmental Officer |
C.M. Wong |
3557 6464 |
|
|
|
Environmental
Supervisor |
Desmond Ho Tsz Ho |
3557 6466 |
|
Leighton Joint Venture |
Contractor under Contract no. HY/2011/08 |
Project Manager |
Paul Evans |
2823 1111 |
21406799 |
Site Agent |
Colman Wong |
9730 0806 |
|||
Environmental
Officer |
David Hung |
9765 6161 |
|||
Environmental Supervisor |
Penny Yiu |
2214 7738 |
|||
ENVIRON
Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
3465 2888 |
3465 2899 |
Lam
Geotechnics Limited |
Environmental
Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3. For
Contract no. HK/2009/01, the principal work activities in this reporting month
included:
Rock trimming
works
2.4.4. For
Contract no. HK/2009/02, the principal work activities in this reporting month
included:
Road works
Connection works
of temporary sewage pipe
Lighting
installation
Granolithic
finishing
Reclamation at
WCR2
Excavation works
Construction of
at-grade road
2.4.5. For
Contract no. HY/2009/15, the principal work activities in this reporting month
included:
EVA construction
at Eastern Breakwater
Reinstatement of
Eastern Breakwater
Removal of
Seawall Blocks at TPCWAE & TS4
Demolition of
D-Wall at TS2, TPCWAE & TS4
Underwater
Cutting of Temporary Diaphragm Walls at TS4 and TPCWAE
2.4.6. For
Contract no. HK/2010/06, the principal work activities in this reporting month
included:
Nil
2.4.7. For
Contract no. HY/2009/19, the principal work activity in this reporting month
included:
Construction of Dolphin Cap
2.4.8. For Contract no. HK/2012/08, the
principal work activity in this reporting month included:
¡P
ELS for box culvert La at Lung King Street
¡P
Filling for seawall rock mound formation
¡P
Filling for reclamation
¡P
Dredging
¡P
Sheet piling
2.4.9. For
Contract no. HY/2010/08, no principal work activities this reporting month.
¡P
Rock filling works
¡P
Dredging works
¡P
Seawall blocks installation
2.4.10. In coming
reporting month, the principal work activities of individual contracts are
anticipated as follows:
Contract no. HK/2009/01 ¡V Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
Rock trimming works
Contract no. HK/2009/02 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East
¡P
Works of covered walkway at Expo Drive East
¡P
Backfilling works
¡P
ABWF works
¡P
Construction of temporary covered walkway
¡P
Installation of Bridge 1, 2 &3
¡P
Construction of at-grade road
¡P
Installation of street furniture and pavement
works
Contract no. HY/2009/15 ¡V Central-Wanchai Bypass ¡V
Tunnel (Causeway Bay Typhoon Shelter Section)
¡P
Construction works of Est Ventilation Shaft
¡P
Removal of Seawall Blocks at TPCWAE & TS4
¡P
Demolition of D-Wall at TPCWAE &TS4
¡P
Underwater Cutting of Temporary Diaphragm
Walls at TS4 and TPCWAE
Contract no. HK/2010/06 ¡V Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Nil
Contract no. HY/2009/19- Wan Chai Bypass Tunnel
(North Point Section) and Island Eastern Corridor Link
Construction of Dolphin Cap
Contract no. HK/2012/08 ¡V Wan Chai Development
Phase II ¡V Central- Wan Chai Bypass at Wan Chai West
¡P
ELS for box culvert La at Lung King Street
¡P
Filling for seawall rock mound formation
¡P
Filling for reclamation
Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass
(CWB) ¡VTunnel (Slip Road 8)
¡P
Rock filling works
¡P
Dredging works
¡P
Seawall blocks installation
3.1.1. A summary
of the current status on licences and/or permits on environmental protection
pertinent to the Project is shown in Table 3.1.
Permits and/or
Licences |
Reference No. |
Issued Date |
Status |
Environmental Permit |
EP-356/2009 |
30 Jul 2009 |
Valid |
Environmental Permit |
EP-364/2009 |
17 Aug 2009 |
Superseded |
Environmental Permit |
EP-364/2009/A |
4 Aug 2010 |
Superseded |
Environmental Permit |
EP-364/2009/B |
20 Sep 2012 |
Superseded |
Environmental Permit |
EP-364/2009/C |
11 Jul 2014 |
Valid |
Environmental Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental
Permit |
FEP-01/356/2009 |
18 Feb 2010 |
Surrendered |
Further Environmental
Permit |
FEP-02/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental
Permit |
FEP-03/356/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
Valid |
Further Environmental Permit |
FEP-01/364/2009 |
24 Mar 2010 |
Valid |
Further Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
Valid |
Further Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
Surrendered |
Further Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
Surrendered |
Further Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-07/364/2009/B |
20 Sep 2012 |
Valid |
Further Environmental Permit |
FEP-08/364/2009/A |
15 Jun 2012 |
Valid |
Further Environmental Permit |
FEP-06/356/2009 |
5 Mar 2013 |
Valid |
Further Environmental Permit |
FEP-07/356/2009 |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-10/364/2009/B |
26 July 2013 |
Valid |
Further Environmental Permit |
FEP-11/362/2009/B |
2 May 2014 |
Valid |
3.1.2. Due to the
multi-contract nature of the Project, the status of permits and/or licences
under the individual contract(s) are presented as below:
Contract
no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at
HKCEC
3.1.3. Summary of
the current status on licences and/or permits on environmental protection
pertinent and submission for contract no. HK/2009/01 under FEP-02/356/2009 are
shown in Table 3.4 and Table 3.5.
Table
3.4 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
06 Jan 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for non-piling equipment |
GW-RS0111-14 |
11 Feb 2014 |
15 Feb 2014 to 14 Aug 2014 |
Expired |
GW-RS0765-14 |
30 Jul 2014 |
15 Aug 2014 to 14 Feb 2015 |
Valid |
|
|
GW-RS0200-14 |
18 Mar 2014 |
21 Mar 2014 to 15 Sept 2014 |
Valid |
|
GW-RS0317-14 |
7 Apr 2014 |
8 Apr 2014 to 7 Oct 2014 |
Valid |
|
GW-RS0362-14 |
17 Apr 2014 |
20 Apr 2014 to 8 Oct 2014 |
Valid |
|
GW-RS0381-14 |
8 Apr 2014 |
9 May 2014 to 11 Nov 2014 |
Valid |
|
GW-RS0435-14 |
30 Apr 2014 |
13 May 2014 to 12 Nov 2014 |
Valid |
|
GW-RS0437-14 |
7 May 2014 |
8 May 2014 to 7 Nov 2014 |
Valid |
|
GW-RS0451-14 |
5 May 2014 |
12 May 2014 to 11 Nov 2014 |
Valid |
|
GW-RS0462-14 |
17 Apr 2014 |
18 Apr 2014 to 17 Oct 2014 |
Valid |
|
GW-RS0498-14 |
22 May 2014 |
24 May 2014 to 22 Nov 2014 |
Replaced by GW-RS0875-14 |
GW-RS0875-14 |
21 Aug 2014 |
23 Aug 2014 to 21 Feb 2015 |
Valid |
|
Discharge Licence |
WT00018110-2014 |
6 Jan 2014 |
31 Mar 2015 |
Valid |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
|
|
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
Billing account under Waste Disposal
Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Dumping
Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined
Marine Disposal) |
EP/MD/14-010 |
24
Apr 2014 |
01
Jun 2014 to 30
Jun 2014 |
Expired |
Table
3.5 Summary of submission status under
FEP-02/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
13 Apr 2010 |
Condition 2.7 |
Works Schedule and
Location Plan |
8 Apr 2010 |
Condition 2.8 |
Silt Curtain
Deployment Plan (Rev. 5) |
24 Aug 2012 |
Silt Curtain
Deployment Plan (Rev. 4) |
12 July 2012 |
|
Silt Curtain
Deployment Plan (Rev. 3) |
27 June 2012 |
|
Silt Curtain
Deployment Plan |
19 Apr 2010 |
|
Condition 2.9 |
Silt
Screen Deployment Plan (Rev. 6) |
20 Aug
2014 |
Silt Screen
Deployment Plan (Rev.5) |
24 Jul 2013 |
|
Silt Screen
Deployment Plan (Rev.4) |
15 Nov 2012 |
|
Silt Screen
Deployment Plan |
19 Apr 2010 |
|
Conditions 2.8 and
2.9 |
Supplementary
Document on Silt Curtain and Silt Screen Deployment Plan |
19 Jul 2010 |
Report on Field
Testing for Silt Curtain |
26 Aug 2010 |
|
Report on Field
Testing for Silt Curtain (Rev. A) |
15 Nov 2010 |
|
Condition 2.12(d) |
Alternative
Proposal on Concurrent Dredging for Sewage Pipeline and Cross Harbour Water
Mains |
15 Apr 2011 |
Condition 2.17 |
Noise Management
Plan |
23 Apr 2010 |
Condition 2.18 |
Landscape Plan
(Erection of Decorative Screen Hoarding along Construction Site around Hong
Kong Exhibition and Convention Centre) |
15 May 2010 |
|
Landscape Plan
(Night-time Lighting) |
22 Oct 2010 |
|
Landscape Plan
(Rev. B) |
15 Nov 2010 |
Condition 1.12 |
Notification of
Commencement Date |
20 Jun 2011 |
Condition 2.6 to
2.8 |
Management
Organization, Works Schedule and Location Plan |
18 May 2011 |
Condition 2.9 |
Silt Screen
Deployment Plan |
10 Jun 2011 |
Condition 2.18 |
Landscape Plan |
31 Oct 2013 |
Contract no. HK/2009/02 ¡V Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
3.1.4. Summary of the current status on licences and/or permits on
environmental protection pertinent and submission for contract no. HK/2009/02
under FEP-03/356/2009 are shown in Table 3.6 and Table 3.7.
Table
3.6 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
|
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0067-14 |
29 Jan 2014 |
15 Feb 2014 to 14 Aug 2014 |
Expired |
GW-RS0112-14 |
13 Jan 2014 |
16 Feb 2014 to 13 Aug 2014 |
Expired |
|
GW-RS0161-14 |
7 Mar 2014 |
11 Mar 2014 to 10 Sep 2014 |
Valid |
|
GW-RS0162-14 |
7 Mar 2014 |
20 Mar 2014 to 19 Sep 2014 |
Valid |
|
GW-RS0233-14 |
21 Mar 2014 |
25 Mar 2014 to 24 Sep 2014 |
Valid |
|
GW-RS0269-14 |
28 Mar 2014 |
7 Apr 2014 to 6 Oct 2014 |
Valid |
|
GW-RS0319-14 |
7 Apr 2014 |
18 Apr 2014 to 17 Oct 2014 |
Valid |
|
|
GW-RS0407-14 |
25 Apr 2014 |
28 Apr 2014 to 16 Oct 2014 |
Valid |
GW-RS0421-14 |
30 Apr 2014 |
30 Apr 2014 to 15 Oct 2014 |
Valid |
|
GW-RS0460-14 |
9 May 2014 |
10 May 2014 to 9 Nov 2014 |
Valid |
|
GW-RS0491-14 |
16 May 2014 |
17 May 2014 to 16 Nov 2014 |
Valid |
|
GW-RS0494-14 |
16 May 2014 |
22 May 2014 to 21 Nov 2014 |
Valid |
|
GW-RS0482-14 |
13 May 2014 |
14 May 2014 to 6 Nov 2014 |
Valid |
|
GW-RS0461-14 |
9 May 2014 |
10 May 2014 to 9 Nov 2014 |
Valid |
|
GW-RS0422-14 |
30 Apr 2014 |
2 May 2014 to 16 Oct 2014 |
Valid |
|
GW-RS0515-14 |
26 May 2014 |
29 May 2014 to 25 Nov 2014 |
Valid |
|
GW-RE0565-14 |
30 May 2014 |
30 May 2014 to 29 Nov 2014 |
Valid |
|
GW-RS0637-14 |
26 Jun 2014 |
2 Jul 2014 to 25 Nov 2014 |
Valid |
|
|
GW-RS0742-14 |
25 Jul 2014 |
15 Aug 2014 to 14 Feb 2015 |
Valid |
|
GW-RS0745-14 |
25 Jul 2014 |
14 Aug 2014 to 13 Feb 2015 |
Valid |
|
GW-RS0840-14 |
18 Aug 2014 |
23 Aug 2014 to 22 Sep 2014 |
Valid |
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
||
WT00006673-2010 |
14 May 2010 |
31 Mar 2015 |
Cancelled |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
WT00007129-2010 |
28 July 2010 |
31 Jul 2015 |
Valid |
|
WT00008982-2011 |
26 Apr 2011 |
30 April 2016 |
Valid |
|
WT00009691-2011 |
1 Aug 2011 |
31 July 2016 |
Valid |
|
Billing Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance (Marine) |
7011496 |
6 Oct 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/15-046 |
24 Jun 2014 |
1 Jul 2014 to 31 Dec 2014 |
Valid |
Dumping Permit (Type 2 ¡V Confined Marine Disposal) |
EP/MD/15-089 |
14 Aug 2014 |
23 Aug 2014 to 22 Sep 2014 |
Valid |
Table
3.7 Summary of submission status under
FEP-03/356/2009 Condition
EP Condition |
Submission |
Date of Submission |
Condition 1.12 |
Commencement Date
of Construction of Marine Works |
8 April 2010 |
Condition 2.6 |
Management
Organization of Main Construction Companies |
10 April 2010 |
Condition 2.7 |
Works Schedule and
Location Plans |
8 April 2010 |
Condition 2.8 |
Silt Curtain
Deployment Plan (Revision A) |
20 April 2010 |
Silt Curtain
Deployment Plan (Revision B) |
25 May 2010 |
|
Silt Curtain
Deployment Plan (Revision C) |
14 Jun 2010 |
|
Silt Curtain
Deployment Plan (Revision H) |
15 Feb 2011 |
|
Silt Curtain
Deployment Plan (Revision I) |
17 Nov 2011 |
|
Silt Curtain
Deployment Plan (Revision J) |
15 Feb 2012 |
|
Silt Curtain
Deployment Plan (Revision K) |
3 May 2012 |
|
Silt Curtain
Deployment Plan (Revision L) |
25 Oct 2012 |
|
Silt Curtain
Deployment Plan (Revision M) |
30 Nov 2012 |
|
Condition 2.9 |
Silt Screen
Deployment Plan |
21 April 2010 |
Supplementary
Information for Existing WSD Salt Water Intakes at Quarry Bay and Sai Wan Ho |
5 Oct 2010 |
|
Silt Screen
Deployment Plan (Revision B) |
15 Feb 2012 |
|
Silt Screen
Deployment Plan (Revision C) |
3 May 2012 |
|
Silt Screen
Deployment Plan (Revision D) |
10 Dec 2012 |
|
Condition 2.17 |
Noise Management
Plan |
6 May 2010 |
Condition 2.18 |
Landscape Plan
(Decorative Screen Hoarding) |
11 May 2010 |
Landscape Plan
(Control of Night Time Lighting) |
2 June 2010 |
|
Landscape Plan
(Combined Version) |
20 July 2011 |
|
Landscape Plan
(Combined Version) |
5 Aug 2011 |
|
----- |
Acknowledge of
Submission |
22 Aug 2011 |
Contract no. HY/2009/15 ¡V Central-Wanchai
Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)
3.1.5. Summary of
the current status on licences and/or permits on environmental protection
pertinent and submission for contract no. HY/2009/15 under EP-356/2009 are
shown in Table 3.8 and Table 3.9.
Table
3.8 Cumulative Summary of Valid Licences
and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise
Permit (CNP) for concreting works at Eastern Breakwater of CBTS |
GW-RS0095-14 |
10 Feb
2014 |
19 Feb 2014 to 18 Aug 2014 |
Expired |
Construction Noise
Permit (CNP) for Pre-treatment, ELS and rock breaking works at TS4/ME4 |
GW-RS0649-14 |
26 Jun
2014 |
1 Jul 2014 to 31 Dec 2014 |
Cancelled |
Construction Noise
Permit (CNP) for D-wall cutting and seawall removal works at TS4/ME4 |
GW-RS0721-14 |
16 Jul 2014 |
18 Jul 2014 to 15 Jan 2015 |
Valid |
Construction Noise
Permit (CNP) for maintenance dredging |
GW-RS0368-14 |
22 Apr 2014 |
1 May 2014 to 31
Oct 2014 |
Valid |
Construction Noise
Permit (CNP) for P3 Mooring |
GW-RS0191-14 |
12 Mar 2014 |
12 Mar 2014 to 11 Sep 2014 |
Valid |
Registration as a
Chemical Waste Producer |
WPN5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste Disposal
Ordinance |
7011553 |
30 Sep 2010 |
27 Sep 2010
to 27 Jan
2016 |
Valid |
Billing Account under Waste Disposal
Ordinance (Dumping by Vessel) |
7011761 |
30 Jun 2014 |
17 Jul 2014 to 16 Oct
2014 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/15-063 |
16 Jul 2014 |
28 Jul 2014 to 27 Jan 2015 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea
Disposal(Dedicated Site) and Type 2 ¡V Confined Marine Disposal) |
EP/MD/15-055 |
9 Jul
2014 |
13 Jul 2014 to 12 Aug 2014 |
Valid |
|
EP/MD/15-085 |
12 Aug
2014 |
15 Aug 2014 to 14 Sep 2014 |
Valid |
Dumping Permit (Type 3 ¡V Special
Treatment/Disposal contained in Geosynthetic Containers) |
EP/MD/15-054 |
11 Jul
2014 |
15 Jul 2014 to 14 Aug 2014 |
Valid |
Table
3.9 Summary of submission status under
FEP-04/356/2009 Condition
FEP Condition |
Submission |
Date of Submission |
Condition 2.6 |
Management Organization of Main Construction
Companies |
30 Sep 2010 |
Amendment for Management Organization of Main
Construction Companies |
16 May 2011 |
|
Condition 2.7 |
Works Schedule and Location Plans |
27 Oct 2010 |
|
Amendment for Works Schedule and Location Plans |
12 Nov 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan |
30 Nov 2010 |
|
Amendment for Silt Curtain Deployment Plan |
24 Feb 2011 |
Amendment for Silt Curtain Deployment Plan |
11 May 2011 |
|
Amendment for Silt Curtain Deployment Plan |
11 Sep 2012 |
|
Amendment for Silt Curtain Deployment Plan |
30 Oct 2012 |
|
Condition 2.9 |
Silt Screen
Deployment Plan |
19 Oct 2010 |
Amendment for Silt Screen Deployment Plan |
18 Feb 2011 |
|
Amendment for Silt Screen Deployment Plan |
15 Jun 2011 |
|
Condition 2.18 |
Proposal
for the Removal of Odorous Sediment and Slime |
13 Jan 2011 |
Amendment for Proposal for the Removal of
Odorous Sediment and Slime |
8 Mar 2011 |
|
|
Amendment for Proposal for the Removal of
Odorous Sediment and Slime |
2 Aug 2011 |
Condition 2.21 |
Landscape Plan |
18 Feb 2011 |
Condition 2.23 |
Noise Management Plan |
20 Oct 2010 |
Amendment for Noise Management Plan |
27 Jan 2011 |
3.1.6. Implementation
status of the recommended mitigation measures during this reporting period is
presented in Appendix 3.1.
Contract no. HK/2010/06 ¡V Wan Chai
Development Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line
3.1.7. Summary of
the current status on licences and/or permits on environmental protection
pertinent and submission for contract no. HK/2010/06 under EP-356/2009 is shown
in Table 3.10 and Table 3.11.
Table
3.10 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2010/06
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/
Expiry Date |
Status |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
N/A |
Valid |
FEP-08/364//2009/A |
15 June
2012 |
N/A |
Valid |
|
Notification of Works Under APCO |
326344 |
18 Jan 2011 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling
equipment |
PP-RS0030-13 |
19 Dec 2013 |
6 Jan 14 ¡V 5 Jul 14 |
Expired |
Billing Account under Waste Disposal
Ordinance |
7012338 |
16 Feb 2011 |
N/A |
Valid |
Table
3.11 Summary of
submission status under EP-356/2009 and FEP-05/356/2009 Condition
EP Condition |
Submission |
Date
of Submission |
Condition 2.23 |
Noise Management Plan |
11 March 2011 |
Condition 2.6 |
Management Organization of Main Construction Companies |
29 April 2013 |
Condition 2.7 |
Works Schedule and Location Plans |
11 March 2011 |
Condition 2.8 |
Revised Silt Curtain Deployment Plan |
31 August 2011 |
Revised Silt Curtain Deployment Plan |
22 October 2012 |
|
Revised Silt Curtain Deployment Plan |
26 November 2012 |
|
Revised Silt Curtain Deployment Plan |
28 January 2013 |
|
Condition 2.9 |
Silt Screen Deployment Plan |
11 April 2011 |
Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
3.1.8. Summary of
the current status on licences and/or permits on environmental protection
pertinent for contract no. HY/2009/19 is shown in Table 3.12.
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/19
Permit / Licence / Notification /
Approval |
Reference No. |
Issued Date |
Valid Period / Expiry date |
Status |
Further Environmental Permit |
FEP-07/364/2009/B |
20 Sep 2012 |
Granted |
Valid |
Notification of Works Under APCO |
326160 |
24 Jan 2011 |
Notified |
Valid |
Construction Noise
Permit (CNP) (For Portion Vi Marine) |
GW-RS10073-14 |
06-Feb-14 |
02-Aug-14 |
Cancelled |
|
GW-RS0507-14 |
23-May-14 |
14-Nov-14 |
Valid |
Discharge License (Sea) |
WT00010865-2011 |
03 Nov 2011 |
30-Nov-16 |
Valid |
C&D Waste Disposal |
7012306 |
10 Feb 2011 |
Registered |
- |
Vessel Disposal |
7013285 |
21 July 2011 |
Registered |
- |
Registration as Chemical Waste Producer |
5213-151-C3654-01 |
24 Mar 2011 |
Registered |
- |
Contract no. HK/2012/08 ¡V Wan Chai Development Phase
II ¡V Central- Wan Chai Bypass at Wan Chai West
3.1.9. Summary of
the current status on licences and/or permits on environmental protection
pertinent and submission for contract no. HK/2012/08 under EP-356/2009 are
shown in Table 3.13 and Table 3.14.
Table 3.13 Cumulative Summary of Valid Licences and Permits under Contract no. HK/2012/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-06/356/2009 |
5 Mar 2013 |
N/A |
Valid |
Notification of Works Under APCO |
355439 |
4 Feb 2013 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
5213-134-C3790-01 |
8 Mar 2013 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7016883 |
18 Feb 2013 |
18 Jul 2017 |
Valid |
Water Discharge Licence |
WT00018223-2014 |
28 Jan 2014 |
31 Jan 2019 |
Valid |
Construction Noise Permit |
GW-RS0193-14 |
13 Mar 2014 |
27 Mar 2014 to 26 Sep 2014 |
Valid |
|
GW-RS0232-14 |
21 Mar 2014 |
23 Mar 2014 to 20 Sep 2014 |
Valid |
|
GW-RS0257-14 |
26 Mar 2014 |
28 Mar 2014 to 25 Sep 2014 |
Valid |
|
GW-RS0293-14 |
1 Apr 2014 |
1 Apr 2014 to 30 Sep 2014 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/15-039 |
1 Jul 2014 |
31 Dec 2014 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type
2 ¡V Confined Marine disposal) |
EP/MD/15-059 |
15 Jul 2014 |
24 Aug 2014 |
Expired |
|
EP/MD/15-087 |
11 Aug 2014 |
24 Sep 2014 |
Valid |
Table
3.14 Summary of submission
status under EP-356/2009 and FEP-06/356/2009
Condition
FEP Condition |
Submission |
Date of Submission |
Condition 2.8 |
Silt Curtain Deployment Plan (Rev. 3) |
Submitted
on 25 Nov 2013 was returned to CSLJV by EPD. |
Condition 2.9 |
Silt Screen Deployment Plan (Rev. 2) |
Generally
in order as commented by EPD on 19 Sep 2013 |
Condition 2.23 |
Noise Management Plan (Rev. 2) |
Generally in order as commented by EPD on 15 Aug 2013 |
Condition 2.24 |
Landscape Plan (Rev. 3) |
Generally
in order as commented by EPD on 31 Oct 2013 |
Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass
(CWB) ¡VTunnel (Slip Road 8)
3.1.10. Summary of
the current status on licences and/or permits on environmental protection
pertinent and submission for contract no. HY/2010/08 under EP-356/2009 are
shown in Table 3.15 and Table 3.16.
Table 3.15 Cumulative Summary of
Valid Licences and Permits under Contract no. HY/2010/08
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-07/356/2009 |
26 Jul 2013 |
NA |
Valid |
|
FEP-10/364/2009/B |
26 Jul 2013 |
NA |
Valid |
Notification of Works Under APCO |
357176 |
2 Apr 2013 |
NIL |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-147-C1169-44 |
27 Mar 2013 |
NIL |
Valid |
Billing Account under Waste Disposal Ordinance |
7017170 |
27 Mar 2013 |
NIL |
Valid |
Water Discharge Licence |
WT00016561-2013 |
9 Jul 2013 |
31 Jul 2018 |
Valid |
Construction Noise Permit |
GW-RS0701-14 |
4
Jul 2014 |
31
Dec 2014 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
EP/MD/15-033 |
9
Jun 2014 |
9
Dec 2014 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type
2 ¡V Confined Marine disposal) |
EP/MD/15-056 |
15
Jul 2014 |
14
Aug 2014 |
Expired |
|
EP/MD/15-082 |
15
Aug 2014 |
14
Sep 2014 |
Valid |
Table
3.16 Summary of submission
status under EP-356/2009 and FEP-07/356/2009
Condition
FEP Condition |
Submission |
Date of Submission |
Condition 2.8 |
Silt Curtain Deployment Plan (rev02) |
26 Aug 2014 |
Condition 2.9 |
Silt Screen Deployment Plan (rev01) |
29
Nov 2013 |
Condition 2.23 |
Noise Management Plan (rev02) |
25 Mar 2014 |
Condition 2.24 |
Landscape Plant (rev03) |
5 Aug 2014 |
Noise Monitoring Stations
4.1.1. The noise
monitoring stations for the Project are listed and shown in Table 4.1
and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.1 Noise
Monitoring Station
Station |
Description |
M1a |
Harbour Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire
Station |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church
Henrietta Secondary School |
Real-time Noise Monitoring
Stations
4.1.2. The
real-time noise monitoring stations for the Project are listed and shown in Table
4.2 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
4.1.3.
The real-time noise monitoring at RTN2-Oil
Street Community Liaison Centre has been relocated to City Garden Electric
Centre (RTN2a- Electric Centre) on 5 Oct 2012, which is a representative of
noise sensitive receiver- City Garden. The baseline noise level of RTN2a will
adopt the results derived from the baseline noise monitoring conducted in
Electric Centre from 4 December 2009 to 17 December 2009.
4.1.4. As the
land-based piling and filling works- DP3 at Tin Hau had been completed on 3
September 2012 and confirmed by RSS, the real-time noise monitoring results at RTN1
- FEHD Hong Kong Transport Section Whitfield Depot was excluded under
EP-356/2009 since 28 November 2012.
Table 4.2 Real
Time Noise Monitoring Station
District |
Station |
Description |
North Point |
RTN2 |
Oil Street
Community Liaison Centre |
North Point |
RTN2a |
Electric Centre |
l
Real
time noise monitoring results and graphical presentation during night time
period are for information only.
l
RTN2 had been relocated to RTN2a since 5 Oct 2012
Noise Monitoring
Parameters, Frequency and Duration
4.1.5. The construction noise level shall be measured in
terms of the A-weighted equivalent continuous sound pressure level (Leq).
Leq (30 minutes) shall be used as the monitoring parameter for the
time period between 0700 and 1900 hours on normal weekdays. For all other time
periods, Leq (5 minutes) shall be employed for comparison with the
Noise Control Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
4.1.6. Noise
monitoring shall be carried out at all the designated monitoring stations. The
monitoring frequency shall depend on the scale of the construction activities.
The following is an initial guide on the regular monitoring frequency for each
station on a weekly basis when noise generating activities are underway:
¡P
One
set of measurements between 0700 and 1900 hours on normal weekdays.
4.1.7. If
construction works are extended to include works during the hours of 1900 ¡V
0700 as well as public holidays and Sundays, additional weekly impact
monitoring shall be carried out during respective restricted hours periods. Applicable
permits under NCO shall be obtained by the Contractor.
Monitoring Equipment
4.1.8. As
referred to in the Technical Memorandum ™ issued under the NCO, sound level
meters in compliance with the International Electrotechnical Commission
Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications shall be
used for carrying out the noise monitoring. Immediately prior to and following
each noise measurement the accuracy of the sound level meter shall be checked
using an acoustic calibrator generating a known sound pressure level at a known
frequency. Measurements may be accepted as valid only if the calibration level
from before and after the noise measurement agree to within 1.0 dB.
4.1.9. Noise
measurements shall not be made in fog, rain, wind with a steady speed exceeding
5 m/s or wind with gusts exceeding 10 m/s. The wind speed shall be checked with
a portable wind speed meter capable of measuring the wind speed in m/s.
Air Quality Monitoring
Stations
4.2.1. The air
monitoring stations for the Project are listed and shown in Table 4.3 and
Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table
4.3 Air Monitoring Station
Station ID |
Monitoring
Location |
Description |
CMA1b |
Oil Street Community
Liaison Centre |
North Point |
CMA2a |
Causeway Bay Community
Centre |
Causeway Bay |
CMA3a |
CWB PRE Site Office * |
Causeway Bay |
CMA4a |
Society for the
Prevention of Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds
opposite to Pedestrian Plaza |
Wan Chai |
CMA6a |
WDII PRE Site Office * |
Wan Chai |
Remarks:
As per the ENPC meeting in January 2011, the monitoring stations CMA3a ¡V Future
CWB site office at Wanchai Waterfront Promenade and CMA6a ¡V Future AECOM site
office at Work Area were renamed as remark.
Air Monitoring Parameters,
Frequency and Duration
4.2.2. One-hour
and 24-hour TSP levels should be measured to indicate the impacts of
construction dust on air quality. The 24-hour TSP levels shall be measured by
following the standard high volume sampling method as set out in the Title 40
of the Code of Federal Regulations, Chapter 1 (Part 50), Appendix B.
4.2.3. All
relevant data including temperature, pressure, weather conditions, elapsed-time
meter reading for the start and stop of the sampler, identification and weight
of the filter paper, and any other local atmospheric factors affecting or
affected by site conditions, etc., shall be recorded down in detail.
4.2.4. For
regular impact monitoring, the sampling frequency of at least once in every
six-days, shall be strictly observed at all the monitoring stations for 24-hour
TSP monitoring. For 1-hour TSP monitoring, the sampling frequency of at least
three times in every six-days should be undertaken when the highest dust impact
occurs.
Sampling Procedure and
Monitoring Equipment
4.2.5. High
volume samplers (HVSs) in compliance with the following specifications shall be
used for carrying out the 1-hour and 24-hour TSP monitoring:
¡P
0.6
¡V 1.7 m3 per minute adjustable flow range;
¡P
equipped
with a timing / control device with +/- 5 minutes accuracy for 24 hours
operation;
¡P
installed
with elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
¡P
capable
of providing a minimum exposed area of 406 cm2;
¡P
flow
control accuracy: +/- 2.5% deviation over 24-hour sampling period;
¡P
equipped
with a shelter to protect the filter and sampler;
¡P
incorporated
with an electronic mass flow rate controller or other equivalent devices;
¡P
equipped
with a flow recorder for continuous monitoring;
¡P
provided
with a peaked roof inlet;
¡P
incorporated
with a manometer;
¡P
able
to hold and seal the filter paper to the sampler housing at horizontal
position;
¡P
easily
changeable filter; and
¡P
capable
of operating continuously for a 24-hour period.
4.2.6. Initial
calibration of dust monitoring equipment shall be conducted upon installation
and thereafter at bi-monthly intervals. The transfer standard shall be
traceable to the internationally recognized primary standard and be calibrated
annually. The concern parties such as IEC shall properly document the
calibration data for future reference. All the data should be converted into
standard temperature and pressure condition.
Laboratory Measurement /
Analysis
4.2.7. A clean
laboratory with constant temperature and humidity control, and equipped with
necessary measuring and conditioning instruments to handle the dust samples
collected, shall be available for sample analysis, and equipment calibration
and maintenance. The laboratory should be HOKLAS accredited.
4.2.8. An alternative non-HOKLAS
accredited laboratory was set-up
for carrying out the laboratory analysis, the laboratory equipment was approved by the ER on 8 February 2011 and the
measurement procedures were
witnessed by the IEC. Any measurement performed by the laboratory was be demonstrated to the satisfaction
of the ER and IEC. IEC shall regularly audit to the measurement performed by
the laboratory to ensure the accuracy of measurement results.
4.2.9. Filter
paper of size 8¡¨ x 10¡¨ shall be labelled before sampling. It shall be a clean
filter paper with no pinholes, and shall be conditioned in a
humidity-controlled chamber for over 24-hours and be pre-weighed before use for
the sampling.
4.2.10. After
sampling, the filter paper loaded with dust shall be kept in a clean and
tightly sealed plastic bag. The filter paper shall then be returned to the
laboratory for reconditioning in the humidity controlled chamber followed by
accurate weighing by an electronic balance with readout down to 0.1 mg. The
balance shall be regularly calibrated against a traceable standard.
4.2.11. All the
collected samples shall be kept in a good condition for 6 months before
disposal.
impact monitoring for
odour patrol
4.2.12. Odour
patrols along the shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai
Public Cargo Working Area when there is temporary reclamation in Causeway Bay
Typhoon Shelter and/or in the ex-Wan Chai Public Cargo Working Area, or when
there is dredging of the odorous sediment and slime at the south-western corner
of the Causeway Bay Typhoon Shelter. Odour patrols will be carried out at
bi-weekly intervals during July, August and September by a qualified person of
the ET who shall:
¡P
be
at least 16 years of age;
¡P
be
free from any respiratory illnesses; and
¡P
not
be allowed to smoke, eat, drink (except water) or use chewing gum or sweets 30
min
¡P
before
and during odour patrol
4.2.13. Odour
patrol shall be conducted by independent trained personnel / competent persons
patrolling and sniffing around the shore as shown in Figure 4.1 to detect any
odour at the concerned hours (afternoon is preferred for higher daily
temperature).
4.2.14. The
qualified person will use the nose (olfactory sensor) to sniff odours at
different locations. The main odour emission sources and the areas to be
affected by the odour nuisance will be identified.
4.2.15. The
perceived odour intensity is to be divided into 5 levels which are ranked in
the descending order as follows:
¡P
0 ¡V
Not detected. No odour perceived or an odour so weak that it cannot be easily characterized
or described;
¡P
1 ¡V
Slight Identifiable odour, and slight chance to have odour nuisance;
¡P
2 ¡V
Moderate Identifiable odour, and moderate chance to have odour nuisance;
¡P
3 ¡V
Strong Identifiable, likely to have odour nuisance;
¡P
4 ¡V
Extreme Severe odour, and unacceptable odour level.
4.2.16.
The findings including odour intensity, odour
nature and possible odour sources, and also the local wind speed and direction
at each location will be recorded. In addition, some relevant meteorological
and tidal data such as daily average temperature, and daily average humidity,
on that surveyed day will be obtained from the Hong Kong Observatory Station
for reference. The Action and Limit levels for odour patrol are shown in Appendix 6.1.
4.2.17. The
qualified odour patrol member has individual n-butanol thresholds complied with
the requirement of European Standard Method of Air Quality ¡V Determination of
Odour Concentration by Dynamic Olfactometry (EN13725) in the range of 20 to 80
ppb.
4.3.1. The EIA
Report has identified that the key water quality impact would be associated
with the dredging works during the construction phase. Marine water quality
monitoring for dissolved oxygen (DO), suspended solid (SS) and turbidity is
therefore recommended to be carried out at selected WSD flushing water intakes.
The impact monitoring should be carried out during the proposed dredging works
to ensure the compliance with the water quality standards.
4.3.2. The
updated EM&A Manual for EP-356/2009 (Version in March 2011) is approval by
EPD on 29 April 2011. As such, the Action Level and Limit Level for the wet
season (April ¡V September) will be effected and applied to the water quality
monitoring data from 30 April 2011.
Water Quality Monitoring Stations
4.3.3. It is
proposed to monitor the water quality at 3 WSD salt water intakes and 8 cooling
water intakes along the seafront of the Victoria Harbour. The proposed water quality
monitoring stations of the Project are shown in Table 4.4 and Figure 4.1. Appendix 4.1
shows the established Action/Limit Levels for the monitoring works.
Table 4.4 Marine
Water Quality Stations for Water Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD17 |
Quarry Bay |
839790.3 |
817032.2 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C7 |
Windsor House |
837193.7 |
816150.0 |
P1 |
HKCEC
Phase I |
835774.7 |
816179.4 |
P3 |
The Academy of performing Arts |
835824.6 |
816212.0 |
P4 |
Shui on Centre |
835865.6 |
816220.0 |
P5 |
Government
Buildings (Wanchai
Tower / Revenue Tower / Immigration Tower) |
835895.2 |
816215.2 |
RW21-P789 |
Great
Eagle Centre/ Sun Hung Kai Centre/CWB |
836268.0 |
816020.0 |
Water Quality Parameters
4.3.4. Monitoring
of dissolved oxygen (DO), turbidity and suspended solids (SS) shall be carried
out at WSD flushing water intakes and cooling water intakes. DO and Turbidity
are measured in-situ while SS is determined in laboratory.
4.3.5. In
association with the water quality parameters, other relevant data shall also
be measured, such as monitoring location/position, time, sampling depth, water
temperature, pH, salinity, dissolved oxygen (DO) saturation, weather
conditions, sea conditions, tidal stage, and any special phenomena and work
underway at the construction site etc.
Sampling Procedures and
Monitoring Equipment
4.3.6. The
interval between two sets of monitoring should not be less than 36 hours except
where there are exceedances of Action and/or Limit Levels, in which case the
monitoring frequency will be increased. Table 4.5 shows the
proposed monitoring frequency and water quality parameters. Duplicate in-situ
measurements and water sampling should be carried out in each sampling event.
For selection of tides for in-situ measurement and water sampling, tidal range
of individual flood and ebb tides should be not less than 0.5m.
Table 4.5 Marine
Water Quality Monitoring Frequency and Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week
baseline monitoring period |
Three days per week,
at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
During marine construction works |
Three days per week,
at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
After completion of marine construction works |
Three days per week,
at mid-flood and mid-ebb tides |
Turbidity, Suspended
Solids (SS), Dissolved Oxygen (DO), pH, Temperature, Salinity |
Notes:
1.
For selection of tides for in-situ measurement
and water sampling, tidal range of individual flood and ebb tides should be not
less than 0.5m.
2.
Turbidity should be measured in situ whereas SS
should be determined by laboratory.
Dissolved Oxygen and
Temperature Measuring Equipment
4.3.7. The
instrument should be a portable, weatherproof dissolved oxygen measuring
instrument complete with cable, sensor, comprehensive operation manuals, and
use a DC power source. It should be capable of measuring:
¡P
a
dissolved oxygen level in the range of 0-20 mg/l and 0-200% saturation
¡P
a
temperature of 0-45 degree Celsius
4.3.8. It should
have a membrane electrode with automatic temperature compensation complete with
a cable. Sufficient stocks of spare electrodes and cables should be available
for replacement where necessary. (e.g. YSI model 59 meter, YSI 5739 probe, YSI
5795A submersible stirrer with reel and cable or an approved similar
instrument).
4.3.9. Should
salinity compensation not be build-in in the DO equipment, in-situ salinity
shall be measured to calibrate the DO equipment prior to each DO measurement.
Turbidity Measurement
Instrument
4.3.10. The
instrument should be a portable, weatherproof turbidity-measuring instrument
complete with comprehensive operation manual. The equipment should use a DC
power source. It should have a photoelectric sensor capable of measuring
turbidity between 0‑1000 NTU and be complete with a cable (e.g. Hach model
2100P or an approved similar instrument).
Sampler
4.3.11. A water
sampler comprises a transparent PVC cylinder, with a capacity of not less than
2 litres, and can be effectively sealed with latex cups at both ends. The
sampler should have a positive latching system to keep it open and prevent
premature closure until released by a messenger when the sampler is at the
selected water depth (e.g. Kahlsico Water Sampler or an approved similar
instrument).
Sample Container and
Storage
4.3.12. Water
samples for suspended solids measurement should be collected in high-density
polythene bottles, packed in ice (cooled to 4¢XC without being frozen), and
delivered to ALS Technichem (HK) Pty Ltd. as soon as possible after collection
for analysis.
Water Depth Detector
4.3.13. A
portable, battery-operated echo sounder shall be used for the determination of
water depth at each designated monitoring station. This unit can either be
handheld or affixed to the bottom of the workboat, if the same vessel is to be
used throughout the monitoring programme.
Salinity
4.3.14. A portable
salinometer capable of measuring salinity in the range of 0-40 ppt shall be
provided for measuring salinity of the water at each of monitoring location.
Monitoring Position
Equipment
4.3.15. A
hand-held or boat-fixed type digital Global Positioning System (GPS) with
waypoint bearing indication or other equivalent instrument of similar accuracy
shall be provided and used during monitoring to ensure the monitoring vessel is
at the correct location before taking measurements.
Calibration of In-situ
Instruments
4.3.16. All
in-situ monitoring instrument shall be checked, calibrated and certified by a
laboratory accredited under HOKLAS or equivalent before use, and subsequently
re-calibrated at 3 monthly intervals throughout all stages of the water quality
monitoring. Responses of sensors and electrodes should be checked with
certified standard solutions before each use. Wet bulb calibration for a DO
meter shall be carried out before measurement at each monitoring location.
4.3.17. For the on
site calibration of field equipment by the ET, the BS 127:1993, "Guide to
Field and on-site test methods for the analysis of waters" should be
observed.
4.3.18. Sufficient
stocks of spare parts should be maintained for replacements when necessary.
Backup monitoring equipment shall also be made available so that monitoring can
proceed uninterrupted even when some equipment is under maintenance,
calibration, etc.
4.3.19. Current
calibration certificates of equipments are presented in Appendix 4.2.
Laboratory Measurement /
Analysis
4.3.20. Analysis
of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS
Technichem (HK) Pty Ltd. Water samples of about 1L shall be collected at the
monitoring stations for carrying out the laboratory SS determination. The SS
determination work shall start within 24 hours after collection of the water
samples. The SS determination shall follow APHA 19ed or equivalent methods
subject to the approval of IEC and EPD.
Enhanced Water Quality
Monitoring in the ex-Wan Chai Public Cargo
Working Area and the
Causeway Bay Typhoon Shelter
4.3.21. The
enhanced water quality monitoring and audit programme is to avoid aggravation of
odour nuisance from seawater arising from temporary reclamation in the ex-Wan
Chai Public Cargo Working Area and the Causeway Bay Typhoon Shelter.
4.3.22. Dissolved
oxygen monitoring at the intakes C6 and C7 in Causeway Bay Typhoon Shelter when
there is temporary reclamation in Causeway Bay Typhoon Shelter and at the
south-western and south-eastern corners of the ex-Wan Chai Public Cargo Working
Area. The proposed water quality monitoring stations of the Project are shown
in Table 4.6 and Figure
4.1.
Table
4.6 Marine Water
Quality Stations for Enhanced Water Quality Monitoring
Station |
Location |
C6 |
Excelsior
Hotel |
C7 |
Windsor House |
Ex-WPCWA-SW |
South-western
of the ex-Wan Chai Public Cargo Working Area |
Ex-WPCWA-SE |
South-eastern
of the ex-Wan Chai Public Cargo Working Area |
4.3.23. The
monitoring of dissolved oxygen are to be carried out 3 days per week, at
mid-flood and mid-ebb tides for 3 water depths (1m below water surface,
mid-depth and 1m above sea bed, except where the water depth less than 6m, the
mid-depth may be omitted. If the water depth be equal to or less than 3m, only
the mid-depth will be monitored).
Daily SS Monitoring and 24
hours Turbidity Monitoring System
4.3.24.
During dredging of the sediment at the
south-western corner of the Causeway Bay Typhoon Shelter, daily
monitoring of suspended solids and 24 hour monitoring of turbidity at the
cooling water intakes (C6 and C7) shall be
conducted.
4.3.25.
The 24 hours monitoring of turbidty at the
cooling water intakes (C6 and C7) shall be established
by setting up a continuous water quality monitoring station in front of the
intakes during the dredging activities. The monitoring system include the
turbidity sensor and data logger which is capable of data capturing at every 5 minutes. The data sahll be downloaded daily and compared with the
Action and Limit level determined during the baseline water qualtiy monitoring
at the cooling water intake locations.
Additional Dissovled
oxygen Monitoring FOR CULVERT L WATER DISCHARGE FLOW
4.3.26.
In response to the Condition 2.18 of the Environmental Permit no.
EP-356/2009 requiring that a silt curtain / impermeable barrier system be
installed to channel water discharge flow from Culvert L to locations outside
the embayment area, a proposed replacement of the requirement with additional
dissolved oxygen monitoring has been conducted at three monitoring stations,
namely A, B and C between the eastern seawall of Central Reclamation Phase III
and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level
between the eastern seawall of Central Reclamation Phase II and the HKCEC
extension could be continuously monitored.
4.3.27.
With respect to the commencement of dredging works under HK/2012/08 and
the installation of MTR precast protection unit, the enhanced water quality
monitoring for Culvert L was temporarily suspended since 24 July 2013
4.3.28.
The monitoring of dissolved oxygen are to be
carried out once per week, at mid-flood and mid-ebb tides for 3 water depths (1m
below water surface, mid-depth and 1m above sea bed, except where the water
depth less than 6m, the mid-depth may be omitted. If the water depth be equal
to or less than 3m, only the mid-depth will be monitored).
5.0.1. The
environmental monitoring will be implemented based on the division of works
areas of each designed project managed under different contracts with separate
FEP applied by individual contractors. Overall layout showing work areas of
various contracts, latest status of work commencement and monitoring stations
is shown in Figure 2.1 and Figure 4.1. The monitoring
results are presented in according to the Individual Contract(s).
5.0.2. In the
reporting month, the concurrent contracts are as follows:
Contract no. HK/2009/01 ¡V
Wan Chai Development Phase II ¡V Central-Wan Chai Bypass at Hong Kong Convention
and Exhibition Centre; and
Contract no. HK/2009/02 Wan
Chai Development Phase II ¡V Central-Wan Chai Bypass at Wan Chai East
Contract no. HY/2009/15 -
Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter Section)
Contract no. HK/2010/06 Wan
Chai Development Phase II ¡V Central-Wan Chai Bypass over MTR Tsuen Wan Line
Contract no. HY/2009/19- Central-
Wan Chai Bypass Tunnel (North Point Section) and Island Eastern Corridor Link
Contract no. HK/2012/08 ¡V
Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan Chai West
Contract no. HY/2010/08 ¡V
Central- Wanchai Bypass Tunnel (Slip Road 8 Section)
5.0.3. The
environment monitoring schedules for reporting month and coming month are
presented in Appendix 5.1.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC, Contract no. HK/2009/02 - Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East and Contract
no. HK/2010/06 Wan Chai Development Phase II ¡V Central-Wan Chai Bypass over MTR
Tsuen Wan Line
5.1.1.
The proposed division of noise monitoring
stations are summarized in Table 5.2 below.
Table 5.2 Noise Monitoring Station for Contract nos.
HK/2009/01, HK/2009/02 and HK/2010/06
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.2.
Daytime and evening period noise monitoring
was conducted at the Harbour Road Sport Centre in the reporting month.
5.1.3.
No exceedance was recorded in this reporting period. Details of noise monitoring results and
graphical presentation can be referred in
Appendix 5.2
Contract
no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter
Section)
5.1.4.
The noise monitoring for HY/2009/15 was
commenced on 10 November 2010. The proposed division of noise monitoring
stations are summarized in Table 5.3 below.
Table 5.3 Noise Monitoring Station for Contract no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.5.
One limit level exceedance was recorded on 5 August 2014 at M2b ¡V Noon
Day Gun Area in the reporting month.
5.1.6.
Barge operation and concrete breaking works
at TS4 under HY/2009/15 were observed during monitoring on 5 August 2014. It
was considered that the operation of derrick barge and nearby breaking works at
TS4 were the major noise contribution. As such, the limit level exceedance was
concluded as project related. Rectification measures including provision of
noise blanket for breakers and provision of noise screen for engine at the
derrick barrage were implemented by the contractor. Additional monitoring was
conducted and no exceedance was identified.
5.4.1.
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring results and
graphical presentation can be referred in Appendix 5.2.
Contract no. HY/2009/19- Wan Chai Bypass Tunnel
(North Point Section) and Island Eastern Corridor Link
5.1.7.
The proposed division of noise monitoring
stations are summarized in Table 5.4 below.
Table 5.4 Noise Monitoring Station for Contract no. HY/2009/19
Station |
Description |
M4b |
Victoria Centre |
M5b |
City Garden |
M6 |
HK Baptist Church Henrietta Secondary School |
5.1.8.
One limit level exceedance was recorded on 28
July 2014 at M6 ¡V HK Baptist Church Henrietta Secondary School in the reporting
month.
5.1.9.
Major traffic noise observed during
monitoring on 28 July 2014 and it was considered as the major noise
contribution. As such, the limit level exceedance was concluded as non-project
related.
5.1.10.
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 5.2.
Contract
no. HY/2010/08-Central-Wanchi Bypass Tunnel (Slip Road 8 Section)
5.1.11.
The proposed division of noise monitoring
stations are summarized in Table 5.5
below.
Table 5.5 Noise
Monitoring Station for Contract no. HY/2010/08
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.12.
No exceedance was recorded in this reporting
month.
5.1.13.
Noise monitoring results measured in this
reporting period are reviewed and summarized. Details of noise monitoring
results and graphical presentation can be referred in Appendix 5.2.
Contract no.
HY/2009/19 ¡V Central- Wan Chai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link
5.2.1 As the land-based piling
and filling works- DP3 at Tin Hau had been completed on 3 September 2012 and
confirmed by RSS, the real-time noise monitoring results at FEHD Hong Kong
Transport Section Whitfield Depot was excluded under EP-356/2009 since 28
November 2012.
5.2.2 The real-time noise
monitoring at RTN2-Oil Street Community Liaison Centre has been relocated to
City Garden Electric Centre (RTN2a- Electric Centre) on 5 Oct 2012, which is a representative
of noise sensitive receiver- City Garden. The baseline noise level of RTN2a
will adopt the results derived from the baseline noise monitoring conducted in
Electric Centre from 4 December 2009 to 17 December 2009.
5.2.3 The major work activities
for Contract no. HY/2009/11 was confirmed substantial complete by RSS on 4
January 2012. The construction site was handed over to contractor HY/2009/19 on
31 December 2011 and the FEP-01/356/2009 was surrendered on 22 Oct 2012.
5.2.4 Real-time
noise monitoring at FEHD Hong Kong Transport Section Whitfield Depot commenced
external wall renovation since 1 June 2012
Table 5.6 Real
Time Noise Monitoring Station for Contract no. HY/2009/19
District |
Station |
Description |
North Point |
RTN2a |
Electric Centre |
l
Real
time noise monitoring results and graphical presentation during night time
period are for information only.
l
RTN2 had been relocated to RTN2a since 5 Oct 2012
l
RTN1 monitoring had been finished on 28 Nov 2012
5.2.5 Limit level
exceedances were recorded at RTN2a-Electric Centre during daytime on 5, 13, 16,
21 and 23 August 2014 and during restricted hours on 1 August 2014 in the
reporting month. After checking with Contractor, bored piling was conducted at
the concerned location on 5, 13 and 16 during the recorded period and bored
piling and breaking works was conducted on 21 and 23 August 2014, contractor
mitigation measures including erection of temporary noise barrier was in place.
In view of the exceedances are non-continuous, the exceedances are considered
to be non-project related and contributed by nearby IEC traffic. On 1 August
2014, bored piling was conducted at the concerned location during the
monitoring period. Temporary noise barrier was implemented by the Contractor
and the CNP GW-RS0752-14 was in place and complied. The exceedance was
considered as non-project related and considered to be contributed by nearby
IEC traffic.
5.2.6
Details of real time noise monitoring results
and graphical presentation can be referred to Appendix 5.5.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.3.1. Air
monitoring was commenced on 1 April 2011 in response to the commencement of the
land-filling work for Contract no. HK/2009/01. The proposed divisions of air
monitoring stations are summarized in Table 5.7 below. No
exceedance was recorded in the reporting month.
Table
5.7 Air
Monitoring Stations for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to Pedestrian Plaza |
CMA6a |
WDII PRE Site Office |
5.3.1 No
exceedance was recorded in the reporting month. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
5.3.2. Air
monitoring was commenced in mid-January 2011 for the land-filling work for
Contract no. HK/2009/02. The proposed division of air monitoring stations are
summarized in Table 5.8 below. No exceedance was
recorded in the reporting month.
Table 5.8 Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Contract
no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter
Section)
5.3.3. Air
monitoring was commenced on 15 March 2011 for the land filling work for
Contract no. HY/2009/15. The proposed division of air monitoring stations are
summarized in Table 5.9 below.
Table
5.9 Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site
Office |
5.3.4. No
exceedance was recorded in the reporting month. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix 5.3.
5.3.5. The odour patrol
along the odour route with 7 sniffing locations was conducted by a qualified
odour patrol member on 5 and 19 August 2014 at the concerned hours (afternoon
for higher daily temperature). No Action and Limit Level was recorded during
this reporting month. The details of the odour patrol results and
meteorological conditions and on the date of odour patrol are shown in Appendix 5.3.
Contract
no. HY/2009/19- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
5.3.6. The
proposed division of air monitoring stations are summarized in Table 5.10
below. No exceedance was recorded in the reporting month.
Table 5.10 Air Monitoring Stations for Contract no.
HY/2009/19
Station |
Description |
CMA1b |
Oil Street Site
Office |
CMA2a |
Causeway Bay
Community Centre |
5.3.7.
No exceedance was recorded in the reporting
month. Air quality monitoring results measured in this reporting period are
reviewed and summarized. Details of
air monitoring results and graphical presentation can be referred in Appendix 5.3.
Contract no. HK/2012/08- Wan Chai Development Phase
II ¡V Central-Wan Chai Bypass at Wan Chai West
5.3.8. The
proposed division of air monitoring stations are summarized in Table 5.11
below. No exceedance was recorded in the reporting month.
Table 5.11 Air Monitoring Stations for Contract no. HY/2012/08
Station |
Description |
CMA5a |
Children Playgrounds opposite to Pedestrian Plaza |
5.3.9. No
exceedance was recorded in the reporting month. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix
5.3.
Contract no. HY/2010/08- Central-Wanchai Bypass
Tunnel (Slip Road 8 Section)
5.3.10. The
proposed division of air monitoring stations are summarized in Table 5.12
below. No exceedance was recorded in the reporting month.
Table 5.12 Air Monitoring Stations for Contract no.
HY/2009/19
Station |
Description |
CMA3a |
CWB PRE Site Office |
5.3.11. No
exceedance was recorded in the reporting month. Air quality monitoring results
measured in this reporting period are reviewed and summarized. Details of air monitoring results and
graphical presentation can be referred in Appendix
5.3.
5.4.1. Due to the hoisting of amber rainstorm warning
signal, the following water quality monitoring events were cancelled.
WQM during flood tide was cancelled on 1 August
2014
WQM during ebb tide was cancelled on 13 August 2014
WQM during ebb tide was cancelled on 20 August 2014
5.4.2. Action and Limit level of water
quality monitoring was transited from dry season to wet season from 1 April
2014.
5.4.3. According to CWB RSS, oil dispersion at the culvert outfall
location at SW corner of CBTS was observed on 6, 22, 24 and 28 Feb 2014. An ICC
case (ICC ref: 2-92821253) regarding the above issue was lodged by CWB RSS team
to request for follow-up action by relevant departments.
5.4.4. Another oil dispersion at the culvert outfall location at
Ex-Cargo handling area was observed on 28 Feb 2014 by CWB RSS. An ICC case (ICC
ref: 2-125779508) regarding the above observation was lodged by CWB RSS team to
request for follow-up action by relevant departments.
5.4.5. With respect to the switching over of cooling water intake
location, the water quality monitoring at the relocated intake station
RW21-P789 under HK/2009/02 was commenced since 29 July 2013 and monitoring
station C5e and C5w were temporarily suspended and switched over to monitoring
station RW21-P789 on 29 July 2013 due to suspension of pump house operation.
5.4.6.
As advised by WDII RSS, the water quality monitoring for WSD21 pump
station with respect to HK/2009/02 was switched over to the relocated location
since 12 March 2014. According to the EM&A Manual, the water quality
monitoring station WSD21 was relocated to station RW21-P789 and the water
quality monitoring at station WSD21 was temporarily suspended since 12 March
2014.
5.4.7.
WQM events on 22 April 2013 at monitoring stations C2, C3, C4e and C4w
were temporarily suspended. Upon confirmation with WDII RSS and the IEC, water
quality monitoring at relocated intakes monitoring location P1, P3, P4 and P5
were commenced since 24 April 2013.
5.4.8.
WDII/RSS advised that the dredging works for submarine pipeline at
Victoria Harbour had been completed in January 2012. Therefore, the concurrent
dredging activities at Sewage Pipeline Zone and reclamation shoreline zone TCBR
under the EP-356/2009 scenario 2B no longer exist. As such, with reference to
Table 5.39 of the EIA Report for Wan Chai Development Phase II and Central-Wan
Chai Bypass, the application of silt screen for cooling water intakes for
Queensway Government Offices was suspended and the others remain unchanged.
5.4.9.
Based on the joint inspection on 4 Jan 2012 for the NPR area, the 4-week
water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9 to confirm no
water deterioration with respect to NPR was commenced since 7 Jan 2012 and it
was completed on 6 February 2012.
5.4.10.
Water quality monitoring at WSD10 and WSD15 was temporary suspended
while water quality monitoring at WSD9 and WSD17 was implemented with respect
to HK/2009/02 from 8 Feb 12 onwards;
5.4.11.
Due to the marine piling under Contract no. HY/2009/19 was completed on
4 March 2013, the temporary suspension of impact water quality monitoring at C8
and C9 from 4 March 2013 have been monitored for 4-week period after the
completion of marine works to confirm no water deterioration.
5.4.12.
The water quality monitoring at the respective monitoring station C8 and
C9 were temporarily suspended from 30 March 2013.
5.4.13.
Based on the safety concern when external façade refurbishment was
conducted by contractor employed by Provident Centre (C9) since 3 Feb 2012,
there is a fine adjustment of the sampling location of water quality monitoring
at C9 to the closest accessible point prior to the completion of the external façade
refurbishment work.
5.4.14. With respect to the trial dredging at WCR2 was scheduled on
20, 22, 24, 25 March and 1, 3 , 11, 13, 15, 17, 19, 20 Apr and 3 May 2012, on-going water quality monitoring results at WSD21
during this period was checked and indicated that there was no contribution due
to the trial dredging operation. Enhanced review of water quality around
WCR2 was also implemented and no deterioration in the water quality was
observed.
5.4.15. Due to the access of water monitoring station at WSD19 was blocked
by LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the
inaccessibility of sampling either land and marine, there is a fine adjustment
of the sampling point of WSD 19 since 5 April 2012 to the closest accessible
point prior to the completion of the construction activities.
5.4.16. Due to the dredging works for Cross Harbour Water Mains from
Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary
suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April
2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for
4-week period after the completion of DP6 to confirm no water deterioration.
5.4.17.
Due to the presence of obstacle within the inner silt curtain frame at
sampling point, water quality point at C7 was finely adjusted to the outside of
the inner silt curtain frame since 29 Dec 2012.
Table 5.13 Water Monitoring Stations for
contracts with respect to remaining DP3
work areas after the completion of DP5 & DP6 in 2012 and intake diversion
in 2013
Contract No. |
Remaining DP3 and work area(s) |
Relevant Water Monitoring Stations, |
Division of WQM w.r.t tentative works commenced / to be commenced |
HK/2009/01 |
WCR3 |
C11 |
Apr 2013 |
HK/2009/02 |
WCR3, WCR4, TWCR4 |
RW21-P7891 |
Apr 2013 |
HK/2012/08 |
HKCEC2W, HKCEC2E |
WSD19, P13, P33, P43, P53 |
Aug 2013 |
HY/2009/15 |
TCBR2, TCBR3, TCBR1W, TPCWAE, TPCWAW |
C64, C7, Ex-WPCWA SW, Ex-WPCWA SE (plus enhanced DO monitoring
described in 4.6.3) |
Nov 2010 |
HY/2010/08 |
TCBR3, TCBR4 |
C64, C7 (plus enhanced DO monitoring described in 4.6.3) |
Mar 2014 |
Remarks:
-The water monitoring stations for WSD19, P1, P3, P4, P5 shall be associated with Contract No. HK/2009/01 prior to their transition to Contract HK/2012/08.
-4 intakes (re-provisioned Wanchai WSD intake, Great Eagle Centre, China Resources Centre & Sun Hung Kai Centre constructed adjacent to each other) taken as a single group for silt screen protection and monitoring.
-Re-provisioned intake reference: P1: HKCEC Phase 1; P3: APA, P4: Shui On; P5: Government Buildings (Wanchai Tower / Revenue Tower / Immigration Tower)
-Enhanced DO Monitoring at
C6 since the intake abandon in May 2011.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.4.18. Water
monitoring for Contract no. HK/2009/01 was commenced on 23 July 2010. The
proposed division of water monitoring stations are summarized in Table
5.14 below.
Table 5.14 Water
Monitoring Stations for Contract no. HK/2009/01
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C1 |
HKCEC
Extension |
835885.6 |
816223.0 |
Remarks:
-
The
water monitoring stations for the dredging works under Contract No. HK/2009/01
should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at
these locations have not been carried out by others. Similarly, the water
monitoring stations for the dredging works under Contract No. HK/2009/02 should
also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations have not been carried out by others.
-
WSD7
and WSD20 water quality monitoring were temporarily suspended since 27 Apr
2012.
-
C2,
C3 C4e and C4w water quality monitoring station was temporarily suspended since
24 Apr 2013
Contract no. HK/2009/02 - Wan Chai Development Wan
Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
5.4.19. Water
monitoring for Contract no. HK/2009/02 was commenced on 8 July 2010. The
proposed division of water monitoring stations are summarized in Table
5.15 below.
Table 5.15 Water
Monitoring Stations for Contract no. HK/2009/02
Station
Ref. |
Location |
Easting |
Northing |
|||
WSD Salt Water Intake |
||||||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
|||
WSD17 |
Quarry Bay |
839790.3 |
817032.2 |
|||
Cooling Water Intake |
||||||
RW21-P789 |
Great Eagle Centre/ Sun Hung Kai Centre/CWB |
836268.0 |
816020.0 |
|||
Remarks:
-
The
water monitoring stations for the dredging works under Contract No. HK/2009/01
should also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at
these locations have not been carried out by others. Similarly, the water
monitoring stations for the dredging works under Contract No. HK/2009/02 should
also include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations has not been carried out by others.
-
Water
quality monitoring at WSD9 and WSD 17 was implemented with respect to
HK/2009/02 from 8 Feb 2012.
-
C5e
and C5w water quality monitoring station was temporarily suspended since 29
July 2013
-
WSD21
water quality monitoring station was temporarily suspended since 12 March 2014
Contract
no. HK/2012/08 - Wan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan
Chai West
5.4.20.
Water monitoring for Contract no. HK/2012/08 was commenced on 5 March
2013. The proposed division of water monitoring stations are summarized in Table 5.16 below.
Table 5.16 Water
Monitoring Stations for Contract no. HK/2012/08
Station
Ref. |
Location |
Easting |
Northing |
|
WSD Salt Water Intake |
||||
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
|
Cooling Water Intake |
||||
P1 |
HKCEC Phase I |
835774.7 |
816179.4 |
|
P3 |
The Academy of
performing Arts |
835824.6 |
816212.0 |
|
P4 |
Shui on Centre |
835865.6 |
816220.0 |
|
P5 |
Government Buildings (Wanchai Tower /
Revenue Tower / Immigration Tower) |
835895.2 |
816215.2 |
|
Contract
no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter
Section)
5.4.21. As the removal of reclamation work
of TS1 at CBTS has been completed, all procedures have been rectified and
complied with the conditions set in EP-356/2009 and FEP-04/356/2009.
5.4.22.
Due to the commencement of the maintenance dredging on 10 November 2010,
water quality monitoring for Contract no. HY/2009/15 was commenced on 9
November 2010. The proposed division of water monitoring stations are
summarized in Table 5.15 below.
5.4.23.
Due to the presence of obstacle within the inner silt curtain frame at
sampling point, water quality point at C7 was finely adjusted to the outside of
the inner silt curtain frame since 29 Dec 2012.
Table
5.17 Water Monitoring
Stations for Contract no. HY/2009/15
Station
Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C7 |
Windsor
House |
837193.7 |
816150.0 |
Remarks: - The cessation of seawater intake operation
for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then
terminated since 17 May 2011.
Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
5.4.24. Due to the
commencement of the marine bored piling on 28 Jan 2012, water quality
monitoring for Contract no. HY/2009/19 was commenced on 28 Jan 2012. The
proposed division of water monitoring stations are summarized in Table 5.16 below.
5.4.26.
Based on the safety concern when external façade refurbishment was
conducted by contractor employed by Provident Center (C9) between 9 January
2012 to 30 July 2012 which caused to the inaccessibility of sampling either
land and marine since 3 Feb 2012, there is a fine adjustment of the sampling
location of water quality monitoring at C9 since 10 March 2012 to the closest
accessible point prior to the completion of the external façade refurbishment
work.
5.4.27.
Due to the access of water monitoring station at WSD19 was blocked by
LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the
inaccessibility of sampling either land and marine, there is a fine adjustment
of the sampling point of WSD 19 since 5 April 2012 to the closest accessible
point prior to the completion of the construction activities.
5.4.28.
As per the meeting with the representative of Excelsior Hotel and World
Trade Centre on 17 May 2011, they confirmed that the seawater intake for The
Excelsior was no longer in use and replaced by the connected permanent water
supply from WSD pipelines since 11 January 2011. Thus, the impact water quality
monitoring for the cooling intake - C6 was terminated effective from 26 May
2011.
5.4.29.
24 hours
monitoring of turbidity at the cooling water intakes at C7 was conducted. With respect to the seawall collapsing at TS4 on 17 November 2011, the
24 hours turbidity monitoring and was kept in November 2011. Since the reinstating the seawall
was completed on 13 January 2012 and no any water deterioration was performed,
24 hour turbidity monitoring was then suspended on 27 January 2012.
5.4.30. Water
monitoring results measured in this reporting period are reviewed and
summarized. Details of water quality monitoring results and graphical
presentation can be referred in Appendix 5.4.
Table 5.18 Summary
of Water Quality Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
|||||||||
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
AL |
LL |
|||
HK/2009/01 |
C1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2012/08 |
WSD19 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
P1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
P3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
P4 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
P5 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
HK/2009/02 Monitoring started
on 8 Feb 2012 |
WSD9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
WSD17 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Monitoring started
on 29 July 2013 |
RW21-P789 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/15 &
HY/2010/08 |
C7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
|
Total |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
||
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
- WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.
-
4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9
were completed on 6 Feb 2012.
- C8 and C9 were
implemented with respect to HY/2009/19 from 28 Jan 2012.
- C8
& C9 was temporary suspended on 30 March 2013 due to the marine works for
Contract no. HY/2009/19 had been completed on 4 March 2013
- WSD7 and WSD20 were
temporarily suspended from 27 Apr 2012
- C2,
C3 C4e and C4w water quality monitoring station was temporarily suspended since
24 Apr 2013
- C5e
and C5w water quality monitoring station was temporarily suspended since 29
July 2013
- WSD21
water quality monitoring station was temporarily suspended since 12 March 2014
- Maintenance
responsibility of silt screen C1, WSD19, P3, P4 and P5 are under Contract
HK/2009/01.
5.4.31.
There were no action level and 1 limit level exceedance of turbidity
recorded in the reporting month. Investigation found that the exceedance was
not related to Project works. The details of recorded exceedance can be
referred to the Section 6.4.
5.4.32.
Enhanced DO monitoring at 4 monitoring stations in Causeway Bay Typhoon
Shelter and Ex-Public Cargo Works Area was conducted three days per week during
the reporting period. The action and limit level exceedances of water quality
monitoring are summarized in Table 5.19.
Table 5.19 Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||
DO |
DO |
||||
AL |
LL |
AL |
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
0 |
0 |
C7 |
0 |
0 |
0 |
0 |
|
Ex-WPCWA
SW |
0 |
6 |
0 |
1 |
|
Ex-WPCWA
SE |
1 |
6 |
0 |
0 |
|
Total |
1 |
12 |
0 |
1 |
5.4.33.
There were 1 action level exceedance and 13 limit level exceedances of
enhanced dissolved oxygen recorded in this reporting month. Investigation found
that the exceedances were not related to the Project works. The details of the
recorded exceedances can be referred to the Section 6.4.
5.4.34.
In response to the Condition 2.18 of the Environmental Permit no.
EP-356/2009 requiring that a silt curtain / impermeable barrier system be
installed to channel water discharge flow from Culvert L to locations outside
the embayment area, a proposed replacement of the requirement with additional
dissolved oxygen monitoring has been conducted at three monitoring stations,
namely A, B and C between the eastern seawall of Central Reclamation Phase III
and the HKCEC Extension since November 2011 under EP-356/2009 so that DO level
between the eastern seawall of Central Reclamation Phase II and the HKCEC
extension could be continuously monitored. Details of additional DO monitoring results
can be referred in Appendix 5.4a.
5.4.35.
With respect to the commencement of dredging works under HK/2012/08 and
the installation of MTR precast protection unit, the enhanced water quality
monitoring for Culvert L was temporarily suspended since 24 July 2013
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.5.1.
No inert C&D waste and non- inert C&D
waste disposed in this reporting month. Details of the waste flow table are
summarized in Table 5.20.
Table 5.20 Details
of Waste Disposal for Contract no. HK/2009/01
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
62116.405 |
TKO137, TM38 |
Inert C&D materials recycled, m3 |
NIL |
5856.5 |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
1673.69 |
|
Non-inert C&D materials recycled, kg |
NIL |
203993 |
N/A |
Chemical waste disposed, kg |
NIL |
10250 |
N/A |
Marine Sediment (Type 1 ¡V Open Sea Disposal), m3 |
NIL (Bulk Volume) |
97428.2 (Bulk Volume) |
South of Cheung Chau |
Marine Sediment (Type 1 ¡V Open Sea
Disposal (Dedicate Sites) & Type 2 ¡V Confined Marine Disposal)
, m3 |
NIL (Bulk Volume) |
52250 (Bulk Volume) |
East of Cha Chau |
Dredged Sediment
Requiring Type 3
¡V Special Treatment / Disposal contained in Geosynthetic Containers |
NIL (Bulk
Volume) |
6773 (Bulk Volume) |
East of Cha Chau |
5.5.2.
There were no marine sediment Type 1- Open
Sea Disposal and no marine sediments Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal disposed
in this reporting month.
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at Wan Chai East
5.5.3.
No Inert C&D waste and Non-inert C&D
waste disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.21.
Table 5.21 Details
of Waste Disposal for Contract no. HK/2009/02
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
263704.45 |
TKO137 / TM 38 |
Inert C&D materials recycled, m3 |
NIL |
18161 |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
1515.103 |
SENT Landfill |
Non-inert C&D materials recycled,
m3 |
N/A |
N/A |
N/A |
Chemical waste disposed, kg |
NIL |
13860 |
SENT Landfill |
Marine Sediment (Type 1 ¡V Open Sea Disposal), m3 |
NIL |
186070 (Bulk volume) |
South of Cheung Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal) , m3 |
NIL |
129320 (Bulk
volume) |
East of Sha Chau |
5.5.4.
There was no Marine Sediment disposed in this
reporting month.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (Causeway Bay Typhoon Shelter Section)
5.5.5.
No Inert C&D waste and no non- inert
C&D waste disposed of in this reporting month. Details of the waste flow
table are summarized in Table 5.22
Table 5.22 Details
of Waste Disposal for Contract no. HY/2009/15
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Remarks |
Inert C&D materials disposed, m3 |
NIL |
141579.2 |
Tuen Mun Area 38 |
NIL |
NIL |
65216 |
TKO137 FB |
NIL |
|
Inert C&D materials recycled, m3 |
NIL |
304 |
ex-PCWA |
NIL |
NIL |
111.9 |
TS4 |
NIL |
|
Non-inert C&D materials disposed, m3 |
NIL |
252.2 |
SENT Landfill |
NIL |
Non-inert C&D materials recycled, kg |
NIL |
299361.5 |
N/A |
NIL |
Chemical waste disposed, kg |
NIL |
8,200 |
N/A |
NIL |
Marine Sediment (Type 1 ¡V
Open Sea Disposal), m3 |
3280 (Bulk Volume) |
103488 (Bulk Volume) |
Cheung Chau South |
Dredging from TCBR1E / TCBR1W / TCBR2/ TCBR3 /
TCBR4 / Maintenance dredging |
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V
Confined Marine Disposal) , m3 |
7380 (Bulk Volume) |
251325 (Bulk Volume) |
East of Sha Chau / South of the Brothers |
Dredging from TCBR1E / TCBR1W / TCBR2/ TCBR3 /
TCBR4 / Maintenance dredging |
Marine
Sediment (Type 3 ¡V Special Treatment / Disposal contained in Geosynthetic
Containers) m3 |
NIL (Bulk Volume) |
12640 (Bulk Volume) |
East of Sha Chau / South of the Brothers |
Dredging from TCBR1W / Maintenance dredging |
Marine
Sediment (Type 2 ¡V Confined Marine Disposal), m3 |
NIL |
9350 (Bulk Volume) |
East of Sha Chau |
Dredging from Eastern Breakwater of CBTS |
Marine Sediment (Type 1 ¡V Open Sea Disposal)
, m3 |
NIL (Bulk Volume) |
600 (Bulk Volume) |
East Sha Chau / South of The Brothers |
Dredging from Phase 3
Mooring Re-arrangement |
Marine Sediment (Type 2¡V Confined Marine Disposal)
, m3 |
NIL (Bulk Volume) |
14,780 (Bulk Volume) |
South of The Brothers |
Dredging from Phase 3
Mooring Re-arrangement |
Marine Sediment (Type 3 ¡V Special Treatment /
Disposal contained in Geosynehetic Containers) , m3 |
NIL (Bulk Volume) |
2,760 (Bulk Volume) |
South of The Brothers |
Dredging from Phase 3
Mooring Re-arrangement |
5.5.6.
There were marine sediment Type 1 ¡V Open Sea
Disposal and Type 1 Open Sea Disposal & Type 2 ¡V Confined Marine Disposal disposed in
this reporting month.
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
5.5.7. No inert C&D
waste was disposed and no non-Inert C&D waste was recycled in this
reporting month. Details of the waste flow table are summarized in Table
5.23.
Table 5.23 Details of Waste Disposal for Contract no. HK/2010/06
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
12567.88 |
TM38 |
Inert C&D materials recycled, m3 |
NIL |
267 |
HK/2009/01 |
Non-inert C&D materials disposed, m3 |
NIL |
369.48 |
SENT/TKO137SF |
Non-inert C&D materials recycled, T |
NIL |
60.58 |
Recyclers |
Chemical waste disposed, L |
NIL |
2600 |
N/A |
Marine Sediment (Type 1 ¡V Open Sea Disposal), m3 |
NIL |
3,891 (Bulk Volume) |
South Cheung Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal) , m3 |
NIL |
12,586 (Bulk Volume) |
East Sha Chau |
5.5.8.
There were no marine sediments Type1- Open
Sea Disposal and no Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V
Confined Marine Disposal was disposed in this reporting month.
Contract no. HY/2009/19 ¡VCentral- WanChai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
5.5.9.
No inert C&D waste and non-inert C&D
waste disposed in this reporting month. Details of the waste flow table are
summarized in Table 5.24.
Table 5.24 Details of Waste Disposal for
Contract no. HY/2009/19
Waste Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
355921.04 |
TM38 |
Inert C&D materials recycled, m3 |
NIL |
59367 |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
1068.6 |
N/A |
Non-inert C&D materials recycled, kg |
NIL |
333.14 |
N/A |
Chemical waste disposed, L |
NIL |
2.12 |
N/A |
Marine Sediment (Type 1 ¡V Open Sea Disposal), m3 |
NIL |
162 |
South Cheung Chau |
Marine Sediment (Type 2 ¡V Confined Marine Disposal) , m3 |
NIL |
681 |
East Sha Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal) , m3 |
NIL |
4976.00 |
|
5.5.10.
There was no marine sediment Type1- Open Sea
Disposal and there was no Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal generated were disposed in this reporting
month.
Contract no. HK/2012/08 ¡VWan Chai Development Phase
II ¡V Central- Wan Chai Bypass at Wan Chai West
5.5.11.
No inert C&D waste was disposed and
non-inert C&D waste were disposed in this reporting month. Details of the
waste flow table are summarized in Table 5.25.
Table 5.25 Details of Waste Disposal for Contract no. HK/2012/08
Waste Type |
Quantity
this month |
Cumulative
Quantity-to-Date |
Disposal
/ Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
1247 |
TM38 |
Inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
315 |
N/A |
Non-inert C&D materials recycled, kg |
NIL |
NIL |
N/A |
Chemical waste disposed, L |
NIL |
NIL |
N/A |
Marine Sediment (Type 1 ¡V
Open Sea Disposal), m3 |
85 (Bulk
volume) |
31759 (Bulk
volume) |
South
of Cheung Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal
(Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3 |
NIL (Bulk
volume) |
108485 (Bulk
volume) |
South
of The Brothers (from 27 Aug 2013 onwards) |
5.5.12.
Marine Sediment Type 1 ¡V Open Sea Disposal was
disposed and no marine sediment Type 1 ¡V Open Sea Disposal (Delicate Sites)
& Type 2 ¡V Confined Marine Disposal was disposed in this reporting month.
Contract
no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip Road 8)
5.5.13.
No Inert C&D waste and non-inert C&D
waste disposed in this reporting month. Details of the waste flow table are
summarized in Table 5.26
Table 5.26 Details of Waste Disposal for Contract no. HY/2010/08
Waste Type |
Quantity
this month |
Cumulative
Quantity-to-Date |
Disposal
/ Dumping Grounds |
Inert C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Inert C&D materials recycled, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials disposed, m3 |
NIL |
NIL |
N/A |
Non-inert C&D materials recycled, kg |
NIL |
NIL |
N/A |
Chemical waste disposed, L |
NIL |
NIL |
N/A |
Dumping Permit (Type 1 ¡V Open Sea Disposal) |
NIL |
16130 |
South Cheung Chau |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate
Sites) & Type 2 ¡V Confined Marine disposal) |
NIL |
17820 |
Brothers Island |
5.5.14.
There was marine sediment Type 1 ¡V Open Sea
Disposal disposed and no Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type
2 ¡V Confined Marine Disposal disposed in this reporting month.
6.0.1. The Event
Action Plan for construction noise, air quality and water quality are presented
in Appendix 6.1.
Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai
Bypass at HKCEC
6.1.1 No
exceedance was recorded in the reporting month.
Contract no.
HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at
WanChai East
6.1.2 No
exceedance was recorded in the reporting month.
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter
Section)
6.1.3 One limit level
exceedance was recorded on 5 August 2014 at M2b ¡V Noon Day Gun Area in the
reporting month.
6.1.4 Barge operation
and concrete breaking works at TS4 under HY/2009/15 were observed during
monitoring on 5 August 2014. It was considered that the operation of derrick
barge and nearby breaking works at TS4 were the major noise contribution. As
such, the limit level exceedance was concluded as project related.
Rectification measures including provision of noise blanket for breakers and
provision of noise screen for engine at the derrick barge were implemented by
the contractor. Additional monitoring was conducted and no exceedance was
identified.
Contract no.
HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR
Tsuen Wan Line
6.1.5
No exceedance was recorded in the reporting
month.
Contract no.
HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link
6.2.1.
Limit level exceedances were recorded at
RTN2a-Electric Centre during daytime on 5, 13, 16, 21 and 23 August 2014 and
during restricted hours on 1 August 2014 in the reporting month. After checking
with Contractor, bored piling was conducted at the concerned location on 5, 13
and 16 during the recorded period and bored piling and breaking works was
conducted on 21 and 23 August 2014, contractor mitigation measures including
erection of temporary noise barrier was in place. In view of the exceedances
are non-continuous, the exceedances are considered to be non-project related
and contributed by nearby IEC traffic. On 1 August 2014, bored piling was
conducted at the concerned location during the monitoring period. Temporary
noise barrier was implemented by the Contractor and the CNP GW-RS0752-14 was in
place and complied. The exceedance was considered as non-project related and
considered to be contributed by nearby IEC traffic.
Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central
¡VWanchai Bypass at HKCEC
6.3.1 No
exceedance was recorded in the reporting month.
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay Typhoon Shelter
Section)
6.3.2 No
exceedance was recorded in the reporting month.
6.3.3 No Action and
Limit Level was recorded for odour patrol during this reporting month.
Contract no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link
6.3.4 No
exceedance was recorded in the reporting month.
Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central
¡VWanchai Bypass at HKCEC
6.4.1 No exceedance was
recorded in this reporting month
Contract
no. HK/2012/08 ¡VWan Chai Development Phase II ¡V Central- Wan Chai Bypass at Wan
Chai West.
6.4.2 No
exceedance was recorded in this reporting month.
Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at WanChai East
6.4.3 No
exceedance was recorded in this reporting month
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (Causeway Bay
Typhoon Shelter Section)
6.4.4 There were
occasionally DO exceedances at Ex-WPCWA SW and Ex-WPCWA SW recorded on 28 July,
3, 4, 6, 11, 13, 25 and 27 August 2014. No odour nuisance was noted during DO
monitoring.
6.4.5 After checking
with Contractor, temporary reclamation removal works were conducted during on the
monitoring dates on 28 July, 3, 4, 6, 11, 13, 25 and 27 August 2014 at Ex-WPCWA.
No dredging works for marine sediments conducted during those monitoring dates.
Contractor mitigation measures including the use of silt curtain was generally
in place. The exceedances were possible in relation to upstream discharge at
the concerned location as it have been consistently observed such that it was
considered the exceedances were not related to Project.
6.4.6 One limit level turbidity
exceedance at C7 cooling water intake monitoring station was recorded on 25
August 2014.
6.4.7 After checking
with contractor¡¦s works, dredging works was conducted during the monitoring
date on 25 August 2014 at Victoria Harbour. Contractor mitigation measures
including use of frame type silt curtain was in place and effective. In
addition, the installed silt screen at monitoring station was properly
maintained. Fine particulates that were observed in the vicinity of monitoring
station and was considered not due to project works as it was possibly in
relation to natural variation or changes of water quality in the vicinity of
water quality monitoring station. Nevertheless, the particulates were cleared
subsequently and turbidity level was restored to normal range within the same
date on 25 August 2014 during flood tide. In the view of exceedance was not
continuous, it was considered not project related.
Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central
¡VWanchai Bypass over MTR Tsuen Wan Line
6.4.8 No
exceedance was recorded in this reporting month.
Contract no. HY/2009/19- Central- Wan Chai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link
6.4.9 No
exceedance was recorded in this reporting month.
Contract no. HK/2012/08- Wan Chai Development Phase II ¡V Central- Wan
Chai Bypass at Wan Chai West
6.4.10 No
exceedance was recorded in this reporting month.
Contract no. HY/2010/08 ¡VCentral - Wan Chai Bypass (CWB) ¡VTunnel (Slip
Road 8)
6.4.11 One limit level turbidity
exceedance at C7 cooling water intake monitoring station was recorded on 25
August 2014.
6.4.12 After checking
with contractor¡¦s works, dredging works was conducted during the monitoring
date on 25 August 2014 at Victoria Harbour. Contractor mitigation measures
including use of frame type silt curtain was in place and effective. In
addition, the installed silt screen at monitoring station was properly
maintained. Fine particulates that were observed in the vicinity of monitoring
station and was considered not due to project works as it was possibly in
relation to natural variation or changes of water quality in the vicinity of
water quality monitoring station. Nevertheless, the particulates were cleared
subsequently and turbidity level was restored to normal range within the same
date on 25 August 2014 during flood tide. In the view of exceedance was not
continuous, it was considered not project related.
6.5.2 No
non-compliances from monitoring was recorded in the reporting month.
7.0.1. According
to Condition 3.4 of the EP-356/2009, this section addresses the relevant
cumulative construction impact due to the concurrent activities of the current
projects including the Central Reclamation Phase III, Central-Wanchai Bypass
and Island Eastern Corridor Link projects.
7.0.3.
According to the construction programme of
Central-Wanchai Bypass at Wanchai West at the Central Reclamation Phase III
area, Diaphragm wall construction and pipe pile wall construction were
performed in August 2014 reporting month. As no project related exceedance were
recorded during the reporting period, cumulative construction impact due to the
concurrent activities of the current projects with the Central Reclamation
Phase III (CRIII) was considered as insignificant.
7.0.4.
According to the construction programme of
Wan Chai Development Phase II, Central-Wan Chai Bypass and Island Eastern
Corridor Link projects, the major construction activity under Wan Chai
Development Phase II were marine works at HKCEC areas, tunnel works at Wan Chai
East and filling works at Wan Chai West. The major construction activities
under Central-Wan Chai Bypass and Island Eastern Corridor Link Projects were bridge
construction and tunnel works at Central Interchange, land base bored pilling
works at Victoria Park Road and ELS, segment launching works and tunnel works
at North Point area. The major environmental impact was water quality impact at
Causeway Bay and Wan Chai. Marine-based construction activities were filling
works at WanChai West and removal of temporary reclamation at TS4, TS2 and
EX-PCWA at Wan Chai East in the reporting month.
7.0.5.
No significant air impact from construction
activities was anticipated in the reporting month. Besides, project related exceedances
were recorded during the air and noise environmental monitoring events in the
reporting month were rectified. Thus, it is evaluated that the cumulative
construction impact from the concurrent projects including Central Reclamation
Phase III (CRIII), Wan Chai Development Phase II (WDII), Central-WanChai Bypass
(CWB), Island Eastern Corridor Link projects (IECL) was insignificant.
8.0.1. During
this reporting month, weekly environmental site audits were conducted for
Contracts no. HK/2009/01,
HK/2009/02, HY/2009/15, HK/2010/06, HY/2009/19, HK/2012/08 and HY/2010/08. No
non-conformance was identified during the site audits.
8.0.2.
Five site inspections for Contract no.
HK/2009/01 were conducted on 30 July, 6, 13, 21 and 27 August 2014 in reporting
month. Results of these inspections and outcomes are summarized in Table
8.1.
Table
8.1 Summary
of Environmental Inspections for Contract no. HK/2009/01
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
140806_01 |
6-Aug-14 |
Drip tray
should be provided for oil container |
The oil
container was taken away and stored in a proper storage area. |
Completion
as observed on 13 August 2014 |
140813_01 |
13-Aug-14 |
Chemical
containers shall be placed and stored properly at Area 8 |
Chemical
containers were stored properly in designated area. |
Completion
as observed on 21 August 2014 |
140827_01 |
27-Aug-14 |
Drip
tray should be provided for oil container at Stage 2 area |
Drip
tray was provided for oil container at Stage 2 area. |
Completion
as observed on 3 September 2014 |
8.0.3.
Four site inspections for Contract no.
HK/2009/02 were carried out on 31 July, 7, 14 and 20 August 2014 in reporting
month. Results of these inspections and outcomes are summarized in Table
8.2.
Table 8.2 Summary
of Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
140731_01 |
31-Jul-14 |
Floating
refuse shall be cleaned up such that the possible of odour nuisance could be minimized. |
Floating
refuses were cleared. |
Completion
as observed on 8 Aug 2014 |
140807_01 |
7-Aug-14 |
Empty oil
cans shall be taken away (Portion 3&4) |
The oil
can was stored in a proper designated area. |
Completion
as observed on 14 Aug 2014 |
140820_01 |
20-Aug-14 |
Drip trays
should be provided for oil chemical containers at Portion 2 |
Drip tray
was provided for oil chemical containers at Portion 2. |
Completion
as observed on 28 Aug 2014 |
8.0.4.
Five site inspections for Contract no.
HY/2009/15 were carried out on 29 July, 5, 12, 19 and 26 August 2014 in reporting
month. The results of these inspections and outcomes are summarized in Table
8.3.
Table
8.3 Summary of
Environmental Inspections for Contract no. HY/2009/15
Date |
Observations |
Action
taken by Contractor |
Outcome |
|
140729_01 |
29-Jul-14 |
Provide impermeable layer at the
dredging work area as per method statement (TS4) |
No further dredging works was
conducted. |
Completion as observed on 26 Aug
2014 |
140729_02 |
29-Jul-14 |
Deploy the silt curtain properly
to prevent seepage of muddy effluent and conduct regular checking of
condition of deployment |
The condition of the silt curtain
was improved |
Completion as observed on 5 Aug
2014 |
140805_01 |
5-Aug-14 |
Drip tray should be provided for
chemical containers (TS4) |
Chemical container has been
removed. |
Completion as observed on 12 Aug
2014 |
140805_02 |
5-Aug-14 |
Silt curtain shall be properly
deployed around the derrick barge (TS4) |
The condition of the silt curtain
was improved |
Completion as observed on 26 Aug 2014 |
140805_03 |
5-Aug-14 |
Acoustic blanket shall be provided
to breakers (TS2) |
Acoustic screen have been provided
to breaker. |
Completion as observed on 12 Aug
2014 |
140805_04 |
5-Aug-14 |
Removal of floating refuse and oil
or grease within embayed water |
Floating refuse and oil or grease
was cleared |
Completion as observed on 12 Aug
2014 |
140812_01 |
12-Aug-14 |
Floating refuses and oil formed on
waterbody shall be cleared (TS4, Ex-pcwa) |
Floating refuse and oil or grease
was cleared |
Completion as observed on 19 Aug
2014 |
140812_02 |
12-Aug-14 |
Drip tray or waste collection
point shall be provided to chemical waste (TS4) |
Chemical container has been
removed. |
Completion as observed on 19 Aug
2014 |
140812_03 |
12-Aug-14 |
Silt curtain shall be provided to
surround the temporary cut slope to prevent muddy seepage (TS2, Ex-pcwa) |
Protection to temporary cut slope
was provided |
Completion as observed on 26 Aug
2014 |
140819_01 |
19-Aug-14 |
Provide noise screen or acoustic
blanket to beaker (TS4) |
Acoustic screen have been provided
to breaker. |
Completion as observed on 26 Aug
2014 |
140826_01 |
26-Aug-14 |
Wastewater collection point shall
be properly connected to prevent surface overflow of construction effluent
(TS4) |
Wastewater collection point has
been rectified, no further surface runoff was observed |
Completion as observed on 2
September 2014 |
140826_02 |
26-Aug-14 |
Silt curtain shall be provided to
the D-wall cutting and filled material excavation to mitigate turbid
dispersion (TS4) |
No further muddy dispersion/
seepage was observed and the D-wall cutting area was provided with silt
curtain |
Completion as observed on 2
September 2014 |
140826_03 |
26-Aug-14 |
Floating refuses and scum shall be
cleaned (TS4, EX-PCWA) |
Floating refuse and scum was
cleared |
Completion as observed on 2
September 2014 |
140826_04 |
26-Aug-14 |
Protection shall be provided to temporary
cut slope to mitigate muddy dispersion (EX-PCWA) |
Protection to temporary cut slope
was provided |
Completion as observed on 2
September 2014 |
8.0.5.
Five site inspections for Contract no. HK/2010/06
were carried out on 28 July, 4, 11, 21 and 25 August 2014 in reporting month.
No particular finding was observed in this reporting month.
8.0.6.
Five site inspections for Contract no.
HY/2009/19 were carried out on 30 July, 6, 13, 20 and 27 August 2014 in
reporting month. The results of these inspections and outcomes are summarized
in Table
8.4.
Table
8.4 Summary of
Environmental Inspections for Contract no. HY/2009/19
Item |
Date |
Observations |
Action
taken by Contractor |
Outcome |
140827_01 |
27-Aug -14 |
Provide dust mitigation measures
to dusty surface |
Watering was provided to dusty
surfaces |
Completion as observed on 3
September 2014 |
8.0.7.
Five site inspections for Contract no.
HK/2012/08 were carried out on 30 July, 5, 12, 19 and 26 August 2014 in this
reporting period. The results of
these inspections and outcomes are summarized in Table 8.5
Table 8.5 Summary
of Environmental Inspections for Contract no. HK/2012/08
Item |
Date |
Observations |
Action
taken by Contractor |
Outcome |
140730_01 |
30-Jul-14 |
Drip tray should be provided for
oil cans. |
Drip tray was provided for oil
cans |
Completion as observed on 5 August
2014 |
140826_01 |
26-Aug-14 |
It is required to identify the
source of muddy water seepage and conduct proper action to prevent any
seepage into the ocean. |
The source of seepage has been
identified and action was taken to prevent any potential seepage. |
Completion as observed on 2 Sep
2014 |
8.0.8.
Four site inspections for Contract no. HY/2010/08
were carried out on 31 July, 8, 14 and 21 July 2014 in this reporting period.
The results of these inspections and outcomes are summarized in Table
8.6.
Table 8.6 Summary
of Environmental Inspections for Contract no. HY/2010/08
Item |
Date |
Observations |
Action
taken by Contractor |
Outcome |
140731_01 |
31-Jul-14 |
Clear the chemical waste container (Victoria Park) |
Chemical waste container have been
removed |
Completion as observed on 8 Aug
2014 |
140808_01 |
8-Aug-14 |
Silt curtain should be properly
deployed to mitigate against muddy seepage (Victoria Park Road) |
The condition of the silt curtain
was improved and properly deployed |
Completion as observed on 14 Aug
2014 |
140821_01 |
21-Aug-14 |
Silt curtain enclosing the
dredging operation shall be properly deployed (TS3) |
Silt curtain for dredging
operation was rectified |
Completion as observed on 28 Aug
2014 |
9.0.1. No
environmental complaint was received in the reporting period.
9.0.2.
The details of cumulative complaint log and updated summary of
complaints are presented in Appendix
9.1
9.0.3. Cumulative
statistic on complaints and successful prosecutions are summarized in Table
9.1 and Table 9.2 respectively.
Table
9.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement works (Mar 2010) to last
reporting month |
30 |
August 2014 |
0 |
Total |
30 |
Table
9.2 Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1. The
EM&A programme was carried out in accordance with the EM&A Manual
requirements, minor alterations to the programme proposed were made in response
to changing circumstances.
10.0.2.
WDII/RSS advised that the dredging works for submarine pipeline at
Victoria Harbour had been completed in January 2012. Therefore, the concurrent
dredging activities at Sewage Pipeline Zone and reclamation shoreline zone TCBR
under the EP-356/2009 scenario 2B no longer exist. As such, with reference to
Table 5.39 of the EIA Report for Wan Chai Development Phase II and Central-Wan
Chai Bypass, the application of silt screen for cooling water intakes for
Queensway Government Offices was suspended and the others were remains
unchanged.
10.0.3.
As the land-based piling and filling works- DP3 at Tin Hau had been
completed on 3 September 2012 and confirmed by RSS, the real-time noise
monitoring results at FEHD Hong Kong Transport Section Whitfield Depot was
excluded under EP-356/2009 since 28 November 2012.
10.0.4.
The real-time noise monitoring at RTN2-Oil Street
Community Liaison Centre has been relocated to City Garden Electric Centre
(RTN2a- Electric Centre) on 5 Oct 2012, which is a representative of noise
sensitive receiver- City Garden. The baseline noise level of RTN2a will adopt
the results derived from the baseline noise monitoring conducted in Electric
Centre from 4 December 2009 to 17 December 2009.
10.0.5.
Water quality monitoring at WSD10 and WSD15 will be temporary suspended
while water quality monitoring at WSD9 and WSD17 were implemented with respect
to HK/2009/02 for the water quality monitoring scheduled on 8 Feb 12 onwards;
10.0.6.
Due to the marine piling under Contract no. HY/2009/19 was completed on
4 March 2013, the temporary suspension of impact water quality monitoring at C8
and C9 from 4 March 2013 have been monitored for 4-week period after the
completion of marine works to confirm no water deterioration.
10.0.7. Water
quality monitoring at C8 & C9 was temporary suspended on 30 March 2013 due
to the marine works for Contract no. HY/2009/19 had been completed on 4 March
2013, and conclude if any water deterioration had been identified during the
4-week water quality monitoring.
10.0.8.
Based on the safety concern when external façade refurbishment was
conducted by contractor employed by Provident Centre (C9) between 9 January
2012 to 30 July 2012 which caused to the inaccessibility of sampling either
land and marine since 3 Feb 2012, there is a fine adjustment of the sampling
location of water quality monitoring at C9 since 10 March 2012 to the closest
accessible point prior to the completion of the external façade refurbishment
work.
10.0.9.
Due to the access of water monitoring station at WSD19 was blocked by
LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the
inaccessibility of sampling either land and marine, there is a fine adjustment
of the sampling point of WSD 19 since 5 April 2012 to the closest accessible
point prior to the completion of the construction activities.
10.0.10. With respect to the trial dredging at WCR2 was scheduled on
20, 22, 24, 25 March and 1, 3, 11, 13,
15, 17, 19, 20 Apr and 3 May 2012, on-going water quality monitoring results at WSD21
during this period was checked and indicated that there was no contribution due
to the trial dredging operation. Enhanced review of water quality around
WCR2 was also implemented and no deterioration in the water quality was
observed.
10.0.11. Due to the dredging works for Cross Harbour Water Mains from
Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary
suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April
2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for
4-week period after the completion of DP6 to confirm no water deterioration.
10.0.12. The
scheduled construction activities and the recommended mitigation measures for
the coming month are listed in Table 10.1.
Table 10.1 Construction
Activities and Recommended Mitigation Measures in
Coming Reporting Month
Contract No. |
Key Construction Works |
Recommended Mitigation Measures |
HK/2009/01 |
¡P
Rock trimming works |
¡P
To well maintain the mechanical equipments /
machineries to avoid abnormal noise nuisance and dark smoke emission |
HK/2009/02 |
¡P
Works of covered walkway at Expo Drive East ¡P
Backfilling works ¡P
ABWF works ¡P
Construction of temporary covered walkway ¡P
Installation of Bridge 1, 2 &3 ¡P
Construction of at-grade road ¡P
Installation of street furniture and pavement works |
¡P
To cover the dusty material or stockpile by
impervious sheet; ¡P
To well maintain the mechanical equipments /
machineries to avoid abnormal noise nuisance and dark smoke emission ¡P
To conform the installation and setting as in
the silt screen and silt curtain
deployment plan ¡P
Movable noise
barrier shall be deployed for demolition works ¡P
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly ¡P
Review silt screen
deployment and silt curtain deployment and resubmit associate
plans to EPD ¡P
Implement silt
screen and silt curtain in accordance with the associated plans submitted to
EPD. |
HY/2009/15 |
¡P
Construction
works of East Ventilation Shaft ¡P
Removal of Seawall Blocks at
TPCWAE & TS4 ¡P
Demolition of D-Wall at TPCWAE
&TS4 ¡P
Underwater
Cutting of Temporary Diaphragm Walls at TS4 and TPCWAE |
¡P
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly ¡P
Implement silt
curtain in accordance with the associated plans submitted to EPD. |
HK/2010/06 |
¡P
Nil |
¡P
Nil |
HY/2009/19 |
¡P
Construction of Dolphin Cap |
¡P
To space out noisy
equipment and position as far as possible from sensitive receiver. |
HK/2012/08 |
¡P
ELS for box culvert La at Lung
King Street ¡P
Filling for seawall rock mound
formation ¡P
Filling for reclamation |
¡P
To conform the installation and setting as in
the silt screen and silt curtain deployment plan ¡P
To space out noisy
equipment and position as far as possible from sensitive receiver. ¡P
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly |
HY/2010/08 |
¡P
To be updated |
¡P
To conform the installation and setting as in
the silt screen and silt curtain deployment plan ¡P
Daily visual inspection of silt screen and
silt curtain to ensure its operation properly |